3237 N OAKSHIRE DR 90068

Certificate Information: 3237 N OAKSHIRE DR 90068

Application / Permit
22014-10000-01593
Plan Check / Job No.
B22LA06158
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 1ST FLOOR GARAGE AND 2ND STORY STORAGE/WORK-SHOP TO ADU PER LAMC 12.22 A.33 (c)-(d) WITH (N) ADDITION FOR PATIO COVER
Permit Issued
Issued on 1/12/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 MAHNAZ NOURHASHEMI
Corrections Issued 5/3/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 5/10/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 5/11/2022 APPLICANT
Applicant returned to address corrections 12/9/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 1/12/2023 MAHNAZ NOURHASHEMI
No Progress 1/12/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 1/12/2023 MAHNAZ NOURHASHEMI
Issued 1/12/2023 APPLICANT
CofO in Progress 3/14/2025 BRENDAN MORELLI
No Progress 3/16/2025 DEROLD HAUFF
CofO in Progress 3/16/2025 DEROLD HAUFF
Permit Finaled 3/27/2025 DEROLD HAUFF
CofO Issued 3/27/2025 DEROLD HAUFF
Permit Finaled 3/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/15/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 7/15/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 7/18/2022 ROMAN GUTIERREZ
Sewer availability Cleared 7/18/2022 ROMAN GUTIERREZ
Grading Pre-Inspection Cleared 12/9/2022 MAHNAZ NOURHASHEMI
Address approval Cleared 1/12/2023 STEVE MELGAR

Contact Information

Contractor Jkc Construction & Design; Lic. No.: 1007078-B 18880 WELLS DRIVE      TARZANA, CA 91356

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/12/2023 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/22/2023 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/28/2023 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 9/18/2023 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 9/26/2023 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 1/25/2024 Approved BRIAN SULLIVAN
HVAC-Rough 1/25/2024 Approved BRIAN SULLIVAN
PLUMBING-Rough 1/25/2024 Approved BRIAN SULLIVAN
Deputy Steel/Welding 1/26/2024 Conditional Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 2/29/2024 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Approved BRIAN SULLIVAN
Green Building Rough 2/29/2024 Approved BRIAN SULLIVAN
MERV13>=Rough 2/29/2024 Approved BRIAN SULLIVAN
Insulation 3/11/2024 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 3/11/2024 Partial Approval BRIAN SULLIVAN
Shower Pan 3/15/2024 Approved BRIAN SULLIVAN
Drywall Nailing 3/19/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 3/19/2024 Partial Approval BRENDAN MORELLI
Sewer 6/14/2024 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/8/2024 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 8/30/2024 Approved ROY SPAULDING
Gas Test 8/30/2024 Approved ROY SPAULDING
Wood Frame 8/30/2024 Approved ROY SPAULDING
Service/Power Release 9/4/2024 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 9/17/2024 Corrections Issued BRIAN SULLIVAN
Service/Power Release 9/23/2024 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 2/25/2025 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/25/2025 SGSOV Not Ready BRIAN SULLIVAN
Final 3/10/2025 Corrections Issued CRAIG VAUGHAN
Green Building Final 3/10/2025 Approved CRAIG VAUGHAN
MERV13>=Final 3/10/2025 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/10/2025 SGSOV Not Required CRAIG VAUGHAN
Smoke Detectors 3/10/2025 Corrections Issued CRAIG VAUGHAN
Final 3/13/2025 Corrections Issued BRENDAN MORELLI
Smoke Detectors 3/13/2025 Approved BRENDAN MORELLI
Final 3/14/2025 OK to Issue CofO BRENDAN MORELLI