3387 S COLBERT AVE 90066

Certificate Information: 3387 S COLBERT AVE 90066

Application / Permit
22014-10000-01556
Plan Check / Job No.
B22LA06023
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION 65 SF TO (E) 2-STORY SFD
Permit Issued
Issued on 6/30/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2022 APPLICANT
Assigned to Plan Check Engineer 4/15/2022 MINA HABILI
Corrections Issued 4/18/2022 MINA HABILI
Building Plans Picked Up 4/19/2022 APPLICANT
Plan Check Approved 5/17/2022 MINA HABILI
Issued 6/30/2022 APPLICANT
CofO in Progress 3/4/2023 DAVID FEILER
Permit Finaled 3/10/2023 DANIEL ORRANTE
CofO Issued 3/10/2023 DANIEL ORRANTE
Permit Finaled 3/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/27/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 5/4/2022 JENSON LEE
Sewer availability Cleared 5/4/2022 JENSON LEE
Specific Plan Cleared 5/5/2022 VALERIA CEJA
Roof/Waste drainage to street Cleared 5/9/2022 JENSON LEE
Grading Pre-Inspection Cleared 5/17/2022 MINA HABILI

Contact Information

Architect Hamilton,, John Patrick; Lic. No.: C28865 12240 VENICE BLVD SUITE 25      LOS ANGELES, CA 90066
Contractor Made Building Company; Lic. No.: 1086752-B 3419 VIA LIDO STE 173      NEWPORT BEACH, CA 92663
Engineer Lin,, Jason K; Lic. No.: S6095 1529 W LONGHILL DR      MONTEREY PARK, CA 91754

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/14/2022 No Access for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 11/16/2022 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 11/18/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 12/16/2022 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 12/20/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 12/20/2022 Not Ready for Inspection DAVID FEILER
Green Building Rough 12/20/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 12/20/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 12/22/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 12/22/2022 Corrections Issued JOHNNY MIRANDA
Insulation 12/22/2022 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 12/22/2022 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 12/22/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 12/27/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 12/27/2022 Approved JOHNNY MIRANDA
Green Building Rough 12/27/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 12/27/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 12/27/2022 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 12/29/2022 Partial Approval JOHNNY MIRANDA
Insulation 1/10/2023 Approved JOHNNY MIRANDA
Drywall Nailing 1/19/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Final 2/9/2023 Approved HERBERT GIRON
PLUMBING-Final 2/9/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/1/2023 Approved CLAYTON GRAHAM
Final 3/1/2023 OK to Issue CofO CLAYTON GRAHAM
Green Building Final 3/1/2023 Approved CLAYTON GRAHAM
Green Building Rough 3/1/2023 Approved CLAYTON GRAHAM
HVAC-Final 3/1/2023 Approved CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Approved CLAYTON GRAHAM
Smoke Detectors 3/1/2023 Approved CLAYTON GRAHAM