1943 N LAUGHLIN PARK DR 90027
Certificate Information: 1943 N LAUGHLIN PARK DR 90027
- Application / Permit
- 22014-10000-01549
- Plan Check / Job No.
- B22LA05987
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO SINGLE FAMILY DWELLING WITH ATTTACHED GARAGE. CONVERT CRAWL SPACE TO ADDITIONAL LEVEL.
- Permit Issued
- Issued on 5/18/2023
- Issuing Office
- Metro
- Current Status
- Issued on 5/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 4/21/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 4/27/2022 | KEN GILL |
| Applicant returned to address corrections | 3/2/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 3/23/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 3/31/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 5/16/2023 | ARMEN JIVALAGIAN |
| Plan Check Approved | 5/18/2023 | ARMEN JIVALAGIAN |
| Issued | 5/18/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/25/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 5/25/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 5/25/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 5/25/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 5/25/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2022 | JEANIE LAM |
| Miscellaneous | Cleared | 5/28/2022 | RYAN LY |
| Private street | Cleared | 6/3/2022 | RYAN LY |
| Sewer availability | Cleared | 6/14/2022 | JEANIE LAM |
| Distance to fire station | Cleared | 6/18/2022 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 6/18/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 2/8/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/9/2023 | JEANIE LAM |
| GPI Written Notices | Cleared | 3/2/2023 | ARMEN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 3/2/2023 | ARMEN JIVALAGIAN |
| ZA Case | Cleared | 3/7/2023 | RYAN LY |
Contact Information
| Architect | Otjen,, Ty Kurtis; Lic. No.: C22126 | 523 THIRD STREET REDLANDS, CA 92374 |
| Contractor | Hartman Baldwin Inc; Lic. No.: 653340-B | 100 WEST FOOTHILL BLVD CLAREMONT, CA 91711 |
| Engineer | Tang,, Che Leng; Lic. No.: S4433 | 6171 OAKRIDGE CT RANCHO CUCAMONGA, CA 91739 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
| Geologist | Schick,, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Grading | 9/15/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/26/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Grading | 9/28/2023 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 9/28/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Piling/Pier/Caisson | 10/6/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Special/Order Compliance | 10/7/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Piling/Pier/Caisson | 10/12/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/19/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Grading | 10/25/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 10/25/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Grading | 10/26/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 10/26/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Grading | 10/27/2023 | Conditional Approval | DAVID FEILER |
| Piling/Pier/Caisson | 11/2/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Piling/Pier/Caisson | 11/30/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Reinf. Concrete | 12/4/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 12/5/2023 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 12/6/2023 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/17/2024 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 2/13/2024 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 2/13/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 2/15/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 3/21/2024 | Conditional Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 6/3/2024 | Partial Approval | ROY SPAULDING |
| Deputy Drilled-In Anchors | 6/5/2024 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 7/16/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/20/2025 | Corrections Issued | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/20/2025 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/20/2025 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 2/20/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/27/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 2/27/2025 | Approved | CRAIG VAUGHAN |
| Shower Pan | 2/27/2025 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 2/27/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 2/27/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 3/10/2025 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 4/2/2025 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 4/21/2025 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 5/20/2025 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 5/20/2025 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 10/16/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 1/29/2026 | Approved | CRAIG VAUGHAN |
| Final | 1/29/2026 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 1/29/2026 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 1/29/2026 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/29/2026 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 1/29/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 1/29/2026 | Approved | CRAIG VAUGHAN |
| Gas Test | 2/20/2026 | Approved | CRAIG VAUGHAN |
| Final | 5/4/2026 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/4/2026 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 5/4/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 5/18/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 5/18/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 6/3/2026 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2026 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 6/3/2026 | Not Ready for Inspection | CRAIG VAUGHAN |