913 N KING AVE 90744
Certificate Information: 913 N KING AVE 90744
- Application / Permit
- 22014-10000-01548
- Plan Check / Job No.
- B22LA05986
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW GROUND FLOOR ADDITION TO (E) 2-CAR GARAGE FOR (N) 1-CAR GARAGE, NEW COVERED PORCH, AND NEW ADU ON 2ND FLOOR PER LAMC 12.22 A.33 (c)-(d) CUGU- PUBLICLY HABITABLE SPACE
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 5/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/23/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 6/29/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 10/14/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 12/5/2022 | MAHNAZ NOURHASHEMI |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 5/6/2026 | EUGENE CASSIDY |
| Permit Finaled | 5/7/2026 | ANSON MAGLASANG |
| CofO Issued | 5/7/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/7/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/24/2022 | ANA SORIANO |
| Clean Up Green Up | Cleared | 10/24/2022 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2022 | ANA SORIANO |
| Sewer availability | Cleared | 10/26/2022 | ANA SORIANO |
| Low Impact Development | Cleared | 11/28/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 11/28/2022 | ANA SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mobed,, Ashkan; Lic. No.: C92493 | 23450 KITTREDGE ST WEST HILLS, CA 91307 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2023 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 2/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Subgrade | 2/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 2/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 12/12/2023 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 12/12/2023 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 12/12/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 12/12/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 3/7/2024 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Partial Approval | EUGENE CASSIDY |
| Insulation | 3/11/2024 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/26/2024 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Partial Approval | JAMES CHAVEZ |
| Gas Test | 6/26/2024 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/29/2024 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 8/1/2024 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 8/1/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/29/2024 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 8/29/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 8/29/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Deputy Wood Construction | 9/5/2024 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/18/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 2/18/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 2/18/2025 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 2/18/2025 | Approved | EUGENE CASSIDY |
| Insulation | 3/21/2025 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/21/2025 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 3/28/2025 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 4/23/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/21/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/30/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/12/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 12/3/2025 | Approved | JOSEPH MCGARRY |
| Final | 3/18/2026 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/18/2026 | Approved | EUGENE CASSIDY |
| Green Building Final | 3/18/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 3/18/2026 | Approved | EUGENE CASSIDY |
| Final | 4/9/2026 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/9/2026 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Not Ready | EUGENE CASSIDY |
| Final | 4/24/2026 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/24/2026 | SGSOV Approved | EUGENE CASSIDY |
| Final | 5/4/2026 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 5/4/2026 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 5/4/2026 | Approved | EUGENE CASSIDY |