2140 W 78TH PL 90047
Certificate Information: 2140 W 78TH PL 90047
- Application / Permit
- 22014-10000-01539
- Plan Check / Job No.
- B22LA05952
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY ADU (40' X 18', 720 FT sq) PER STATE LAW The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 2/29/2024
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 4/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | GEORGE ALVAREZ |
| Corrections Issued | 4/25/2022 | GEORGE ALVAREZ |
| Building Plans Picked Up | 4/27/2022 | APPLICANT |
| Plan Check Approved | 8/4/2022 | KHUONG TRUONG |
| Issued | 2/29/2024 | APPLICANT |
| CofO in Progress | 4/16/2025 | WAYNE REGESTER |
| Permit Finaled | 4/20/2025 | DEROLD HAUFF |
| CofO Issued | 4/20/2025 | DEROLD HAUFF |
| Permit Finaled | 4/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2022 | JEANIE LAM |
| Sewer availability | Cleared | 5/3/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 6/4/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/4/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 7/7/2022 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 8/23/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/4/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 6/14/2024 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 7/10/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 7/26/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 7/26/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 7/26/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 7/26/2024 | Approved | JOSE MACIAS |
| Sewer | 7/26/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 7/26/2024 | Not Ready for Inspection | JOSE MACIAS |
| Verify Sprinkler Sign Off | 7/26/2024 | Approved | JOSE MACIAS |
| Insulation | 7/30/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 8/2/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 8/2/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 8/2/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 10/3/2024 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Final | 10/4/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 10/15/2024 | Approved | AMIR NAZARIAN |
| Final | 10/15/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 10/15/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Final | 10/15/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Final | 10/15/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Service/Power Release | 10/15/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Smoke Detectors | 10/15/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 10/22/2024 | Approved | AMIR NAZARIAN |
| Final | 10/22/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 10/22/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Final | 10/22/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Approved | AMIR NAZARIAN |
| Service/Power Release | 10/22/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 12/30/2024 | Corrections Issued | AMIR NAZARIAN |
| Service/Power Release | 12/30/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 4/15/2025 | OK to Issue CofO | WAYNE REGESTER |
| Service/Power Release | 4/15/2025 | Approved | WAYNE REGESTER |