514 W 107TH ST 90044

Certificate Information: 514 W 107TH ST 90044

Application / Permit
22014-10000-01537
Plan Check / Job No.
B22LA05947
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of 323 SF accessory dwelling unit to rear of existing 1-story single family dwelling per LAMC 12.22 A.33(c)-(d) and interior remodel to existing 1-story single family dwelling. All work per WFPP.
Permit Issued
Issued on 12/5/2023
Issuing Office
Metro
Current Status
Issued on 12/5/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/5/2022 APPLICANT
Assigned to Plan Check Engineer 4/15/2022 MINA HABILI
Corrections Issued 4/15/2022 MINA HABILI
Building Plans Picked Up 4/19/2022 APPLICANT
Plan Check Approved 11/9/2022 MINA HABILI
No Progress 11/7/2023 STANLEY RAAP
Plan Check Approved 11/7/2023 VICTOR CHEN
Issued 12/5/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/2/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 6/29/2022 ABEL CASILLAS
Sewer availability Cleared 6/29/2022 ABEL CASILLAS
Address approval Cleared 2/13/2023 ABEL CASILLAS
Construction near power lines Cleared 6/5/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/7/2024 Approved BEN MOLSTAD
Footing/Foundation/Slab 11/14/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 12/11/2024 Corrections Issued BEN MOLSTAD
Deputy Drilled-In Anchors 12/12/2024 Partial Approval BEN MOLSTAD
Footing/Foundation/Slab 12/12/2024 Approved BEN MOLSTAD
Pre-Inspection 12/12/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Partial Approval ANTHONY EGSON
Gas Test 12/26/2024 Partial Approval ANTHONY EGSON
PLUMBING-Rough 12/26/2024 Partial Approval ANTHONY EGSON
Insulation 12/30/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 1/8/2025 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 1/30/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 1/30/2025 Approved BEN MOLSTAD
Green Building Rough 1/30/2025 Not Ready for Inspection BEN MOLSTAD
MERV13>=Rough 1/30/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 1/30/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 2/5/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 2/11/2025 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 2/11/2025 Not Ready for Inspection BEN MOLSTAD
MERV13>=Rough 2/11/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 2/11/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 2/12/2025 Approved BEN MOLSTAD
ELECTRICAL-Rough 3/20/2025 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Corrections Issued BEN MOLSTAD
Rough-Elec/Plmb/HVAC 3/20/2025 Approved BEN MOLSTAD
Special/Order Compliance 4/13/2026 Partial Inspection JOSEPH MCGARRY