2014 1/2 N GRIFFIN AVE 90031

Certificate Information: 2014 1/2 N GRIFFIN AVE 90031

Application / Permit
22014-10000-01534
Plan Check / Job No.
B22LA05940
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 6'-0" x 22'-0" AND 8'-0" x 12'-0" ADDITION TO AND CONVERT 12'-0" x 14'-0" EXISTING DETACHED GARAGE TO A NEW 22'-0" x 18'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER WFPP.
Permit Issued
Issued on 9/9/2022
Issuing Office
Current Status
CofO Issued on 8/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2022 APPLICANT
Assigned to Plan Check Engineer 6/10/2022 DANIEL SANJUAN
Corrections Issued 6/11/2022 DANIEL SANJUAN
Applicant returned to address corrections 9/1/2022 DANIEL SANJUAN
Plan Check Approved 9/9/2022 SARKIS HARABEDIAN
Issued 9/9/2022 APPLICANT
CofO in Progress 8/24/2023 OSVALDO PARAMO
CofO in Progress 8/24/2023 OSVALDO PARAMO
Permit Finaled 8/31/2023 RONALD MYRICK
CofO Issued 8/31/2023 RONALD MYRICK
Permit Finaled 8/31/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 7/5/2022 WALLIE JONG
Highway dedication Cleared 7/5/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 7/5/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/6/2022 WALLIE JONG
Sewer availability Cleared 7/6/2022 WALLIE JONG
Tenant Habitability Plan Cleared 7/13/2022 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/19/2022 Partial Inspection RUBEN SALAS
Excavation/Setback/Form/Re-Bar 9/27/2022 Partial Inspection RUBEN SALAS
Sewer 10/11/2022 Approved OSVALDO PARAMO
Underground Mechanical 10/11/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 10/14/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 11/1/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 11/28/2022 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 11/28/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/8/2022 Approved OSVALDO PARAMO
Green Building Rough 12/8/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/8/2022 Partial Approval OSVALDO PARAMO
Insulation 1/6/2023 Approved ALIZAH MAYAGOITIA
Drywall Nailing 1/10/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 3/9/2023 Corrections Issued OSVALDO PARAMO
Final 3/23/2023 Corrections Issued OSVALDO PARAMO
Green Building Final 3/23/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 3/23/2023 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 3/23/2023 Approved OSVALDO PARAMO
Final 5/16/2023 Corrections Issued OSVALDO PARAMO
Final 8/22/2023 OK to Issue CofO OSVALDO PARAMO