18530 W OXNARD ST 91356
Certificate Information: 18530 W OXNARD ST 91356
- Application / Permit
- 22014-10000-01533
- Plan Check / Job No.
- B22LA05935
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- NEW SECOND FLOOR ADDITION INSIDE (E) WAREHOUSE AND OFFICE BUILDING
- Permit Issued
- Issued on 9/12/2023
- Issuing Office
- Current Status
- Issued on 9/12/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | ARSALAN SHABESTARI |
| Disabled Access Plans Picked Up | 5/12/2022 | APPLICANT |
| Corrections Issued | 5/23/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 5/26/2022 | KEN GILL |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| Applicant returned to address corrections | 8/25/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 9/12/2023 | ARSALAN SHABESTARI |
| Issued | 9/12/2023 | APPLICANT |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 10/11/2022 | ARSALAN SHABESTARI |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/25/2022 | LEE GUILBEAUX |
| Highway dedication | Cleared | 11/1/2022 | LEE GUILBEAUX |
| Permit | Cleared | 11/1/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 11/28/2022 | KURT CORRAL |
| Green Code | Cleared | 4/27/2023 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 6/9/2023 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 19528 VENTURA BLVD #300 TARZANA, CA 91356 |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/28/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 11/28/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 12/1/2023 | Conditional Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 12/4/2023 | Partial Inspection | BRIAN KELLY |
| Deputy Reinf. Concrete | 12/6/2023 | Conditional Approval | BRIAN KELLY |
| Wood Frame | 2/20/2024 | Corrections Issued | BRIAN KELLY |
| Wood Frame | 3/14/2024 | Not Ready for Inspection | BRIAN KELLY |
| Insulation | 3/18/2024 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 3/18/2024 | Not Ready for Inspection | BRIAN KELLY |
| Drywall Nailing | 4/8/2024 | Not Ready for Inspection | BRIAN KELLY |
| Drywall Nailing | 5/21/2024 | Not Ready for Inspection | BRIAN KELLY |
| Insulation | 5/21/2024 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 5/21/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 6/5/2024 | Not Ready for Inspection | BRIAN KELLY |
| Footing/Foundation/Slab | 6/5/2024 | Approved | BRIAN KELLY |
| Green Building Final | 6/5/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Rough | 6/5/2024 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 6/5/2024 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 6/5/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 6/13/2024 | No Access for Inspection | BRIAN KELLY |
| Green Building Final | 6/13/2024 | No Access for Inspection | BRIAN KELLY |
| Green Building Rough | 6/13/2024 | No Access for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 6/13/2024 | No Access for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 6/13/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 6/13/2024 | No Access for Inspection | BRIAN KELLY |
| Final | 6/21/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 6/21/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Rough | 6/21/2024 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 6/21/2024 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 6/21/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 6/21/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 7/12/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 7/12/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Rough | 7/12/2024 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 7/12/2024 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 7/12/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 7/12/2024 | Not Ready for Inspection | BRIAN KELLY |
| Pre-Inspection | 7/3/2025 | Partial Inspection | BRIAN KELLY |
| Pre-Inspection | 4/1/2026 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 4/2/2026 | Partial Inspection | DEANDRE HOFFMAN |
| Green Building Final | 4/2/2026 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 4/2/2026 | Approved | DEANDRE HOFFMAN |
| Reinforced Masonry Frame | 4/2/2026 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 4/2/2026 | Approved | DEANDRE HOFFMAN |