4036 E CHEVY CHASE DR 90039
Certificate Information: 4036 E CHEVY CHASE DR 90039
- Application / Permit
- 22014-10000-01515
- Plan Check / Job No.
- B22LA05823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO MAIN HOUSE AND INTERIOR REMODEL OF KITCHEN AND LAUNDRY AREA 2 OF 2
- Permit Issued
- Issued on 10/4/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | ADRIANA LOPEZ |
| Corrections Issued | 5/10/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 6/10/2022 | FARUK SEZER |
| Building Plans Picked Up | 6/14/2022 | APPLICANT |
| Applicant returned to address corrections | 9/14/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 9/28/2022 | ADRIANA LOPEZ |
| Issued | 10/4/2022 | APPLICANT |
| CofO in Progress | 10/10/2023 | HAMIK HARTOUNIAN |
| CofO in Progress | 10/10/2023 | SCOTT FINNILA |
| CofO in Progress | 10/20/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 10/23/2023 | DEROLD HAUFF |
| CofO Issued | 10/23/2023 | DEROLD HAUFF |
| Permit Finaled | 10/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/18/2022 | TREVOR QUAN |
| ZI | Cleared | 7/18/2022 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2022 | TREVOR QUAN |
Contact Information
| Contractor | Harris General Contracting & Construction; Lic. No.: 1022262-B | 2724 GLASSELL ST LOS ANGELES, CA 90026 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/19/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/9/2023 | Approved | SCOTT FINNILA |
| Wood Frame | 5/30/2023 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 6/13/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/13/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 6/13/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/13/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/13/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/15/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/15/2023 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 6/15/2023 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 6/20/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 6/21/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 6/29/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 6/29/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/29/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/19/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/19/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 9/19/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 9/19/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/19/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 10/10/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 10/20/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |