4036 E CHEVY CHASE DR 90039

Certificate Information: 4036 E CHEVY CHASE DR 90039

Application / Permit
22014-10000-01515
Plan Check / Job No.
B22LA05823
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO MAIN HOUSE AND INTERIOR REMODEL OF KITCHEN AND LAUNDRY AREA 2 OF 2
Permit Issued
Issued on 10/4/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 ADRIANA LOPEZ
Corrections Issued 5/10/2022 ADRIANA LOPEZ
Quality Review Completed 6/10/2022 FARUK SEZER
Building Plans Picked Up 6/14/2022 APPLICANT
Applicant returned to address corrections 9/14/2022 ADRIANA LOPEZ
Plan Check Approved 9/28/2022 ADRIANA LOPEZ
Issued 10/4/2022 APPLICANT
CofO in Progress 10/10/2023 HAMIK HARTOUNIAN
CofO in Progress 10/10/2023 SCOTT FINNILA
CofO in Progress 10/20/2023 HAMIK HARTOUNIAN
Permit Finaled 10/23/2023 DEROLD HAUFF
CofO Issued 10/23/2023 DEROLD HAUFF
Permit Finaled 10/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/18/2022 TREVOR QUAN
ZI Cleared 7/18/2022 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 8/18/2022 TREVOR QUAN

Contact Information

Contractor Harris General Contracting & Construction; Lic. No.: 1022262-B 2724 GLASSELL ST      LOS ANGELES, CA 90026
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/19/2023 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/9/2023 Approved SCOTT FINNILA
Wood Frame 5/30/2023 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 6/13/2023 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/13/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 6/13/2023 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 6/13/2023 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 6/13/2023 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 6/15/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 6/15/2023 Approved HAMIK HARTOUNIAN
Wood Frame 6/15/2023 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 6/20/2023 Conditional Approval HAMIK HARTOUNIAN
Insulation 6/21/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/29/2023 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 6/29/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/29/2023 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/19/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 9/19/2023 Approved HAMIK HARTOUNIAN
Final 9/19/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 9/19/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 9/19/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Approved HAMIK HARTOUNIAN
Final 10/10/2023 Partial Approval HAMIK HARTOUNIAN
Final 10/20/2023 OK to Issue CofO HAMIK HARTOUNIAN