376 W CANYON VISTA DR 90065

Certificate Information: 376 W CANYON VISTA DR 90065

Application / Permit
22014-10000-01503
Plan Check / Job No.
B22LA05787
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
KITCHEN, BATHROOM REMODEL AND ENCLOSED COVERED PATIO/ DECK AREA. (172 SQ FT) TO (E) TWO STORY SFD
Permit Issued
Issued on 1/4/2023
Issuing Office
Current Status
CofO Issued on 4/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 HERNAN ARREOLA
Corrections Issued 5/2/2022 HERNAN ARREOLA
Quality Review Completed 5/10/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 5/11/2022 APPLICANT
Applicant returned to address corrections 7/11/2022 HERNAN ARREOLA
Plan Check Approved 8/4/2022 HERNAN ARREOLA
Issued 1/4/2023 APPLICANT
CofO in Progress 4/27/2024 OSVALDO PARAMO
CofO Issued 4/29/2024 DEROLD HAUFF
Permit Finaled 4/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/18/2022 STEVE MELGAR
Specific Plan Cleared 6/6/2022 NASHYA JENSEN
Sewer availability Cleared 6/21/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/22/2022 STEVE MELGAR

Contact Information

Contractor Williams Christopher; Lic. No.: 711380-B P O BOX 8652      LA CRESCENTA, CA 91224

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/21/2023 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 3/21/2023 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 3/21/2023 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 3/30/2023 Partial Approval OSVALDO PARAMO
Insulation 4/5/2023 Partial Approval OSVALDO PARAMO
Wood Frame 4/5/2023 Approved OSVALDO PARAMO
Drywall Nailing 4/11/2023 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 4/17/2023 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 5/31/2023 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 5/31/2023 Partial Approval OSVALDO PARAMO
HVAC-Rough 5/31/2023 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 5/31/2023 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 6/9/2023 Approved OSVALDO PARAMO
Final 6/9/2023 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 6/9/2023 Approved OSVALDO PARAMO
Shower Pan 6/9/2023 Approved OSVALDO PARAMO
Shower Pan 6/14/2023 Approved OSVALDO PARAMO
Final 1/9/2024 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/9/2024 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 1/9/2024 Approved OSVALDO PARAMO
Final 4/22/2024 OK to Issue CofO OSVALDO PARAMO