3632 S BARBARA ST 90731
Certificate Information: 3632 S BARBARA ST 90731
- Application / Permit
- 22014-10000-01500
- Plan Check / Job No.
- B22LA05754
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION AND 2ND STORY ADDITION TO (E) 1-STORY SFD. 1ST FLOOR REMOVE WALLS BETWEEN KITCHEN AND DINING ROOM, REMOVE PARTIAL BACK WALL, PARTIAL REMODEL KITCHEN, NEW MASTER DECK, NEW ROOFING, NEW WINDOWS IN ADDITION ONLY, NEW GLASS SLIDER IN FAMILY ROOM, NEW STAIRCASE, NEW BACK DECK WITH STAIRS
- Permit Issued
- Issued on 12/28/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | ADRIANA LOPEZ |
| Corrections Issued | 5/19/2022 | ADRIANA LOPEZ |
| Building Plans Picked Up | 6/8/2022 | APPLICANT |
| Quality Review Completed | 6/10/2022 | FARUK SEZER |
| Applicant returned to address corrections | 10/18/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 11/2/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 12/18/2023 | ADRIANA LOPEZ |
| Issued | 12/28/2023 | APPLICANT |
| CofO in Progress | 11/20/2024 | JOSEPH MCGARRY |
| CofO Issued | 1/2/2025 | ANSON MAGLASANG |
| Permit Finaled | 1/2/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/5/2022 | KIRK LINKLATER |
| BHO/Hillside ordinance | Cleared | 10/25/2022 | ANA SORIANO |
| BHO/Hillside ordinance | Cleared | 10/25/2022 | ANA SORIANO |
| BHO/Hillside ordinance | Cleared | 10/25/2022 | ANA SORIANO |
| BHO/Hillside ordinance | Cleared | 10/25/2022 | ANA SORIANO |
| BHO/Hillside ordinance | Cleared | 10/25/2022 | ANA SORIANO |
| Sewer availability | Cleared | 10/25/2022 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2022 | ANA SORIANO |
| Low Impact Development | Cleared | 11/29/2023 | MELINEH AGHAKHABIAN |
| ZI | Cleared | 12/7/2023 | MAXFIELD VERMY |
| Coastal Zone | Cleared | 12/12/2023 | MAXFIELD VERMY |
| Roof/Waste drainage to street | Cleared | 12/12/2023 | KHAING AYE |
| GPI Written Notices | Cleared | 12/18/2023 | ADRIANA LOPEZ |
Contact Information
| Contractor | Supreme Remodeling Inc; Lic. No.: 939981-B | 14545 VICTORY BLVD UNIT 401 VAN NUYS, CA 91411 |
| Engineer | Hashemi,, Jafar; Lic. No.: C62010 | 26009 CALMHILL DR TORRANCE, CA 90505 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2024 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 1/22/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Underground Mechanical | 1/30/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2024 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 2/1/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | JAMES CHAVEZ |
| Insulation | 2/15/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/20/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 3/20/2024 | Corrections Issued | JAMES CHAVEZ |
| Green Building Rough | 3/20/2024 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 3/20/2024 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 3/20/2024 | Corrections Issued | JAMES CHAVEZ |
| Shower Pan | 3/20/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 3/26/2024 | Approved | ANSON MAGLASANG |
| HVAC-Rough | 3/26/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 3/26/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Shower Pan | 3/26/2024 | Approved | ANSON MAGLASANG |
| Wood Frame | 3/26/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Rough | 4/3/2024 | Approved | ANSON MAGLASANG |
| HVAC-Rough | 4/3/2024 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 4/3/2024 | Partial Approval | ANSON MAGLASANG |
| PLUMBING-Rough | 4/3/2024 | Approved | ANSON MAGLASANG |
| Shower Pan | 4/3/2024 | Approved | ANSON MAGLASANG |
| Wood Frame | 4/3/2024 | Approved | ANSON MAGLASANG |
| Insulation | 4/9/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Interior/Exterior Lathing | 4/9/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 4/17/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 4/17/2024 | Partial Approval | JAMES CHAVEZ |
| Drywall Nailing | 4/29/2024 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 4/29/2024 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 8/19/2024 | Approved | JOSEPH MCGARRY |
| Final | 8/19/2024 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 8/19/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 8/19/2024 | Approved | JOSEPH MCGARRY |
| Final | 9/11/2024 | Corrections Issued | BEN MOLSTAD |
| Pre-Inspection | 11/8/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 11/20/2024 | OK to Issue CofO | JOSEPH MCGARRY |