123 S CRESCENT HEIGHTS BLVD 90048

Certificate Information: 123 S CRESCENT HEIGHTS BLVD 90048

Application / Permit
22014-10000-01492
Plan Check / Job No.
B22LA05722
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
RENOVATION OF (E) SFD INCCLUDES (N) KITCHEN, (N) BATHROOM, PARTIAL (N) ROOF AND (N) ADDITION, NEW TRELLIS AT (E) DECK. 1 OF 2
Permit Issued
Issued on 3/29/2023
Issuing Office
Valley
Current Status
Issued on 3/29/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/4/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 MICHAEL LOPEZ
Corrections Issued 4/20/2022 MICHAEL LOPEZ
Quality Review Completed 4/25/2022 SAI KHUM
Building Plans Picked Up 4/25/2022 APPLICANT
Applicant returned to address corrections 6/13/2022 MICHAEL LOPEZ
Applicant returned to address corrections 7/25/2022 MICHAEL LOPEZ
Plan Check Approved 9/27/2022 MICHAEL LOPEZ
Issued 3/29/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/3/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 6/3/2022 JEANETTE VONG
Sewer availability Cleared 6/3/2022 JEANETTE VONG

Contact Information

Contractor Liebobuilders; Lic. No.: 1054050-B 18401 BURBANK BLVD SUITE 120      TARZANA, CA 91356
Engineer Wavering,, Derek Evan; Lic. No.: S6239 1371 COLE LANE      UPLAND, CA 91784

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/2/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 5/3/2023 Approved JEREMY TODD
METHANE-Barrier 5/3/2023 Approved JEREMY TODD
METHANE-Subgrade 5/3/2023 Approved JEREMY TODD
PLUMBING-Rough 7/24/2023 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 9/26/2023 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 9/26/2023 Corrections Issued MEL KHACHATOURIAN
Green Building Rough 9/26/2023 Corrections Issued MEL KHACHATOURIAN
HVAC-Rough 9/26/2023 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Rough 9/26/2023 Approved MEL KHACHATOURIAN
PLUMBING-Rough 9/26/2023 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 9/29/2023 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 9/29/2023 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 9/29/2023 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 10/2/2023 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 10/2/2023 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 10/3/2023 Approved MEL KHACHATOURIAN
HVAC-Rough 10/3/2023 Approved MEL KHACHATOURIAN
PLUMBING-Rough 10/3/2023 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 10/6/2023 Approved MEL KHACHATOURIAN
Green Building Rough 10/6/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 10/16/2023 No Access for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 10/19/2023 Partial Approval MEL KHACHATOURIAN
Insulation 10/25/2023 Approved CARLOS MATAMOROS
Shower Pan 11/3/2023 Approved MEL KHACHATOURIAN
Drywall Nailing 11/21/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 11/21/2023 Approved MEL KHACHATOURIAN