8556 N CASABA AVE 91306

Certificate Information: 8556 N CASABA AVE 91306

Application / Permit
22014-10000-01489
Plan Check / Job No.
B22LA05717
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION TO EXISTING HOUSE IN REAR INCLUDING (1) NEW BEDROOM, (1) NEW LAUNDRY ROOM.
Permit Issued
Issued on 9/13/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2022 APPLICANT
Assigned to Plan Check Engineer 4/13/2022 JESSE JIMENEZ
Corrections Issued 4/14/2022 JESSE JIMENEZ
Building Plans Picked Up 4/20/2022 APPLICANT
Plan Check Approved 6/7/2022 RAHEL BEYENE
Issued 9/13/2022 APPLICANT
CofO in Progress 7/21/2023 CHRIS CHRISTENSEN
Permit Finaled 8/30/2023 JOHN JANSON
CofO Issued 8/30/2023 JOHN JANSON
Permit Finaled 8/30/2023 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/13/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/19/2022 MEGAN GODINEZ
Sewer availability Cleared 5/19/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 5/19/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 5/19/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 5/19/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2022 Corrections Issued DAVID SANDOVAL
Deputy Drilled-In Anchors 11/3/2022 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/15/2022 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/23/2023 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 1/23/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/30/2023 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 1/30/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 1/30/2023 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/16/2023 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 2/16/2023 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 2/16/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 2/16/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 2/16/2023 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 2/16/2023 Corrections Issued CHRIS CHRISTENSEN
Drywall Nailing 2/23/2023 Not Ready for Inspection JESUS PINEDA
BUILDING-Rough-Frame 3/7/2023 Conditional Approval JUSTIN HAWLEY
Drywall Nailing 3/7/2023 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 3/7/2023 Approved JUSTIN HAWLEY
HVAC-Final 3/7/2023 Corrections Issued JUSTIN HAWLEY
HVAC-Rough 3/7/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 3/7/2023 Partial Approval JUSTIN HAWLEY
PLUMBING-Rough 3/7/2023 Approved JUSTIN HAWLEY
Special/Order Compliance 3/7/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/31/2023 Corrections Issued CHRIS CHRISTENSEN
Service/Power Release 6/12/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/18/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 7/18/2023 Approved CHRIS CHRISTENSEN
Final 7/18/2023 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/18/2023 Approved CHRIS CHRISTENSEN
Green Building Final 7/18/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 7/18/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Final 7/18/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/18/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 7/18/2023 Approved CHRIS CHRISTENSEN
Final 7/20/2023 OK to Issue CofO CHRIS CHRISTENSEN
HVAC-Final 7/20/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/20/2023 SGSOV Approved CHRIS CHRISTENSEN