14560 W GALLAUDET PL 90272

Certificate Information: 14560 W GALLAUDET PL 90272

Application / Permit
22014-10000-01488
Plan Check / Job No.
B22LA05716
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRST FLOOR LIVING ROOM EXPANSION, AND SECOND FLOOR GAME ROOM ADDITION, SECOND FLOOR JACUZZI AT EXTERIOR DECK.
Permit Issued
Issued on 11/8/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 JAD BASMA
Corrections Issued 5/11/2022 JAD BASMA
Quality Review Completed 5/13/2022 SAI KHUM
Building Plans Picked Up 5/16/2022 APPLICANT
Applicant returned to address corrections 6/2/2022 JAD BASMA
Plan Check Approved 8/23/2022 JAD BASMA
Issued 11/8/2022 APPLICANT
CofO in Progress 8/9/2024 ARAM AVEDISIAN
Permit Finaled 8/30/2024 RICHARD STEINBACH
CofO Issued 8/30/2024 RICHARD STEINBACH
Permit Finaled 8/30/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/12/2022 NIKTA MOUSAVI
Private sewage disp. approval Cleared 7/20/2022 KIRK LINKLATER
Low Impact Development Cleared 8/8/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 8/16/2022 VLADIMIR ARUTYUNYAN
GPI Written Notices Cleared 8/23/2022 JAD BASMA
Grading Pre-Inspection Cleared 8/23/2022 JAD BASMA

Contact Information

Contractor Jvl Construction Services Inc; Lic. No.: 1096790-B 340 S LEMON AVENUE #1680      WALNUT, CA 91789
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/13/2022 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 12/19/2022 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 12/21/2022 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 12/21/2022 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 12/28/2022 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 12/30/2022 Partial Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 12/30/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/4/2023 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 2/9/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Corrections Issued OGANES TARAKHCHYAN
Green Building Rough 4/6/2023 Partial Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/11/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Pre-Inspection 4/12/2023 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/28/2023 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/3/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 5/3/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 5/4/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 5/4/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/5/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/11/2023 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 5/12/2023 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/17/2023 Approved OGANES TARAKHCHYAN
Green Building Rough 5/17/2023 Approved OGANES TARAKHCHYAN
Insulation 5/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 5/23/2023 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Final 10/27/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Final 2/20/2024 Corrections Issued EVAN COOPER
Green Building Final 2/20/2024 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Approved EVAN COOPER
Smoke Detectors 2/20/2024 Approved EVAN COOPER
Final 8/9/2024 OK to Issue CofO ARAM AVEDISIAN