1437 N STANLEY AVE 90046

Certificate Information: 1437 N STANLEY AVE 90046

Application / Permit
22014-10000-01473
Plan Check / Job No.
B22LA05648
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-Plan: Convert existing detached garage (368 SF) to ADU and (N) 91 SF Addition per engineer design (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 8/26/2022
Issuing Office
Current Status
CofO Issued on 5/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2022 APPLICANT
Assigned to Plan Check Engineer 4/12/2022 ARSALAN SHABESTARI
Corrections Issued 4/12/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 6/18/2022 AUNG SOE
Plan Check Approved 6/28/2022 ARSALAN SHABESTARI
Issued 8/26/2022 APPLICANT
CofO in Progress 5/16/2023 STUART CHAPMAN
Permit Finaled 5/19/2023 DEROLD HAUFF
CofO Issued 5/19/2023 DEROLD HAUFF
Permit Finaled 5/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/2/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 5/2/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/6/2022 CELINA MORENO
Sewer availability Cleared 5/6/2022 CELINA MORENO
ZA Case Cleared 5/9/2022 STEVEN WECHSLER
Construction near power lines Cleared 6/10/2022 RIDWAN HARDY
Construction within easement Cleared 6/10/2022 RIDWAN HARDY

Contact Information

Contractor Davda Construction; Lic. No.: 1066309-B       ,
Contractor Pure Energy Construction; Lic. No.: 1066309-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/30/2022 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 9/14/2022 Partial Approval RAUL BARAJAS
Masonry Wall/Backfill 9/22/2022 Approved RAUL BARAJAS
BUILDING-Rough-Frame 11/14/2022 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 11/14/2022 Approved RAUL BARAJAS
PLUMBING-Rough 11/14/2022 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 11/28/2022 Partial Approval BRIAN SULLIVAN
HVAC-Rough 11/28/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 12/6/2022 Approved BRIAN SULLIVAN
Insulation 12/6/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 12/6/2022 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 12/19/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 12/19/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 12/19/2022 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 12/21/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 1/27/2023 Approved STUART CHAPMAN
Final 1/27/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 1/27/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 1/27/2023 Approved STUART CHAPMAN
Final 2/2/2023 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 2/6/2023 Approved STUART CHAPMAN
Final 2/6/2023 Corrections Issued STUART CHAPMAN
HVAC-Final 2/6/2023 Approved STUART CHAPMAN
PLUMBING-Final 2/6/2023 Approved STUART CHAPMAN
Final 5/16/2023 OK to Issue CofO STUART CHAPMAN