1819 W YOSEMITE DR 90041
Certificate Information: 1819 W YOSEMITE DR 90041
- Application / Permit
- 22014-10000-01457
- Plan Check / Job No.
- B22LA05579
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING ONE STORY SFD.
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2022 | TSE MING HUANG |
| Corrections Issued | 4/9/2022 | TSE MING HUANG |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| Plan Check Approved | 5/10/2022 | AUNG SOE |
| Issued | 6/1/2022 | APPLICANT |
| CofO in Progress | 2/13/2023 | CRAIG VAUGHAN |
| CofO Issued | 2/24/2023 | DEROLD HAUFF |
| Permit Finaled | 2/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/22/2022 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 4/25/2022 | CINDY QI |
| Sewer availability | Cleared | 4/25/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/12/2022 | Corrections Issued | CRAIG VAUGHAN |
| Underground Mechanical | 7/12/2022 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 7/14/2022 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/14/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/12/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 8/12/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/12/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/12/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/12/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/12/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/12/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/24/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 8/24/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/24/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/24/2022 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/24/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/31/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/31/2022 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/8/2022 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/8/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/15/2022 | Approved | SCOTT FINNILA |
| Insulation | 9/20/2022 | Approved | CRAIG VAUGHAN |
| Shower Pan | 9/23/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/27/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 9/27/2022 | Approved | AMY COLIN |
| Final | 1/31/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 1/31/2023 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 1/31/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/2/2023 | Corrections Issued | CRAIG VAUGHAN |
| Final | 2/6/2023 | Conditional Approval | RUBEN SALAS |
| ELECTRICAL-Final | 2/10/2023 | Approved | CRAIG VAUGHAN |
| Final | 2/10/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 2/10/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 2/10/2023 | Approved | CRAIG VAUGHAN |