12360 W HORTENSE ST 91604
Certificate Information: 12360 W HORTENSE ST 91604
- Application / Permit
- 22014-10000-01450
- Plan Check / Job No.
- B22LA05550
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION TO ACCESSORY DWELLING UNIT AND ADDITION. per 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)(d)(g)
- Permit Issued
- Issued on 11/28/2022
- Issuing Office
- Valley
- Current Status
- Issued on 11/28/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | GEORGE ALVAREZ |
| Corrections Issued | 4/11/2022 | GEORGE ALVAREZ |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Plan Check Approved | 10/21/2022 | KHUONG TRUONG |
| Issued | 11/28/2022 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 6/21/2022 | DWAYNE LAURENT |
| Address approval | Cleared | 6/23/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 7/28/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/28/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/26/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/29/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 9/29/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Lando General Construction Inc; Lic. No.: 1071910-B | 11001 GLORIA AVE GRANADA HILLS, CA 91344 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/13/2022 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Pre-Inspection | 12/14/2022 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 1/12/2023 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 2/22/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 3/7/2023 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 4/5/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 4/6/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 4/24/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 4/24/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 4/24/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 4/24/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Sewer | 4/24/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 4/25/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Sewer | 4/25/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 4/25/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 4/26/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/27/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/20/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/20/2023 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 10/20/2023 | Approved | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 10/23/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/31/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/2/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 11/8/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 11/27/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/19/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Shower Pan | 12/19/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/21/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 12/21/2023 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/16/2024 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 5/16/2024 | Approved | CHRISTOPHE COCHRAN |