6109 S ALVISO AVE 90043

Certificate Information: 6109 S ALVISO AVE 90043

Application / Permit
22014-10000-01428
Plan Check / Job No.
B22LA05435
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert existing Garage with addition to create ADU per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 8/10/2022
Issuing Office
Current Status
CofO Issued on 4/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2022 APPLICANT
Assigned to Plan Check Engineer 6/17/2022 SAMUEL GONZALEZ
Corrections Issued 6/19/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 7/18/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 7/22/2022 RICARDO RAMIREZ
Plan Check Approved 7/30/2022 ZAW HAN
Issued 8/10/2022 APPLICANT
CofO in Progress 4/26/2023 ENRIQUE MIRELES
CofO in Progress 4/26/2023 ENRIQUE MIRELES
Permit Finaled 4/29/2023 DEROLD HAUFF
CofO Issued 4/29/2023 DEROLD HAUFF
Permit Finaled 4/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/24/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 6/24/2022 JEANETTE VONG
Grading Pre-Inspection Cleared 6/30/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 7/8/2022 JEANETTE VONG
Sewer availability Cleared 7/12/2022 JEANETTE VONG

Contact Information

Contractor L A Developing Inc; Lic. No.: 1083426-B 2926 CUDAHY STREET      HUNTINGTON PARK, CA 90255

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/16/2022 Approved ENRIQUE MIRELES
Sewer 8/18/2022 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 9/2/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 9/7/2022 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 9/13/2022 Corrections Issued ANTHONY EGSON
Gas Test 9/13/2022 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 9/13/2022 SGSOV Not Ready ANTHONY EGSON
Underground Mechanical 9/13/2022 Partial Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 9/16/2022 Approved ENRIQUE MIRELES
Gas Test 9/16/2022 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 10/11/2022 Approved ENRIQUE MIRELES
Deputy Wood Construction 10/11/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/16/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/16/2022 Approved ENRIQUE MIRELES
Green Building Rough 11/16/2022 Approved ENRIQUE MIRELES
HVAC-Rough 11/16/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/16/2022 Approved ENRIQUE MIRELES
Drywall Nailing 11/30/2022 Approved JAMES CHAVEZ
Interior/Exterior Lathing 11/30/2022 Approved JAMES CHAVEZ
Final 2/2/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/2/2023 Approved ENRIQUE MIRELES
Green Building Final 2/2/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 2/2/2023 Approved ENRIQUE MIRELES
Final 2/10/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 2/15/2023 Approved ENRIQUE MIRELES
Final 2/15/2023 OK to Issue CofO ENRIQUE MIRELES
HVAC-Final 2/15/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 2/15/2023 Approved ENRIQUE MIRELES
Service/Power Release 2/15/2023 Approved ENRIQUE MIRELES