6109 S ALVISO AVE 90043
Certificate Information: 6109 S ALVISO AVE 90043
- Application / Permit
- 22014-10000-01428
- Plan Check / Job No.
- B22LA05435
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing Garage with addition to create ADU per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Current Status
- CofO Issued on 4/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 6/19/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 7/18/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 7/22/2022 | RICARDO RAMIREZ |
| Plan Check Approved | 7/30/2022 | ZAW HAN |
| Issued | 8/10/2022 | APPLICANT |
| CofO in Progress | 4/26/2023 | ENRIQUE MIRELES |
| CofO in Progress | 4/26/2023 | ENRIQUE MIRELES |
| Permit Finaled | 4/29/2023 | DEROLD HAUFF |
| CofO Issued | 4/29/2023 | DEROLD HAUFF |
| Permit Finaled | 4/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 6/24/2022 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 6/30/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/12/2022 | JEANETTE VONG |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | 2926 CUDAHY STREET HUNTINGTON PARK, CA 90255 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/16/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 8/18/2022 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 9/2/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/7/2022 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/13/2022 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 9/13/2022 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Underground Mechanical | 9/13/2022 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/16/2022 | Approved | ENRIQUE MIRELES |
| Gas Test | 9/16/2022 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 10/11/2022 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 10/11/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/16/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/16/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 11/16/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/16/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/16/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/30/2022 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 11/30/2022 | Approved | JAMES CHAVEZ |
| Final | 2/2/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/2/2023 | Approved | ENRIQUE MIRELES |
| Green Building Final | 2/2/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/2/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/10/2023 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/15/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/15/2023 | OK to Issue CofO | ENRIQUE MIRELES |
| HVAC-Final | 2/15/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 2/15/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 2/15/2023 | Approved | ENRIQUE MIRELES |