4129 N KRAFT AVE 91604

Certificate Information: 4129 N KRAFT AVE 91604

Application / Permit
22014-10000-01427
Plan Check / Job No.
B22LA05423
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1-STORY MASTER BEDROOM/MASTER BATHROOM/CLOSET ADDITION TOWARD REAR OF (E) SFD WITH ATTACHED GARAGE. INCLUDES REMODEL OF SFD PORTION.
Permit Issued
Issued on 5/5/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2022 APPLICANT
Assigned to Plan Check Engineer 4/6/2022 LAWRENCE QUIRANTE
Corrections Issued 4/7/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 5/1/2022 AUNG SOE
Plan Check Approved 5/2/2022 AUNG SOE
Issued 5/5/2022 APPLICANT
Building Plans Picked Up 5/5/2022 APPLICANT
CofO in Progress 6/4/2025 JAVIER RAMOS JR
CofO Issued 8/15/2025 RUBEN SALAS
Permit Finaled 8/15/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/20/2022 DAGOVERTO GUERRERO
Supp. Use District POD/CDO/TDO Cleared 4/25/2022 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 4/26/2022 DAGOVERTO GUERRERO

Contact Information

Architect Buckley,, Bryce James; Lic. No.: C37052 201 N GRAND AVENUE      PASADENA, CA 91103
Contractor Hartman Baldwin Inc; Lic. No.: 653340-B 100 WEST FOOTHILL BLVD      CLAREMONT, CA 91711
Engineer Mutka,, Jason Richard; Lic. No.: C72255 PO BOX 77144      CORONA, CA 92877

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/30/2023 Approved RUBEN SALAS
Footing/Foundation/Slab 10/30/2023 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 2/29/2024 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 2/29/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 2/29/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 3/6/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 3/6/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 3/6/2024 Corrections Issued KIRK SANDERS
Wood Frame 3/6/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 3/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/8/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/8/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 3/19/2024 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 3/19/2024 Partial Approval KIRK SANDERS
Insulation 3/27/2024 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 4/3/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/3/2024 Partial Approval CHRISTOPHER ROJAS
Shower Pan 4/3/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Corrections Issued CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 12/11/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 1/15/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/15/2025 Partial Inspection CHRISTOPHER ROJAS
Green Building Rough 1/15/2025 Partial Inspection CHRISTOPHER ROJAS
HVAC-Rough 1/15/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 1/15/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/16/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 1/16/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 1/16/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Partial Approval CHRISTOPHER ROJAS
Insulation 1/27/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/30/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/30/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/11/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 2/11/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 2/11/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 6/3/2025 Approved JAVIER RAMOS JR
Final 6/3/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 6/3/2025 Approved JAVIER RAMOS JR
HVAC-Final 6/3/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 6/3/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 6/3/2025 Approved JAVIER RAMOS JR