11012 N QUILL AVE 91040

Certificate Information: 11012 N QUILL AVE 91040

Application / Permit
22014-10000-01404
Plan Check / Job No.
B22LA05298
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/23/2022
Issuing Office
Current Status
CofO Issued on 1/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2022 APPLICANT
Assigned to Plan Check Engineer 4/5/2022 GEORGE ALVAREZ
Corrections Issued 4/11/2022 GEORGE ALVAREZ
Building Plans Picked Up 4/11/2022 APPLICANT
Plan Check Approved 6/17/2022 SHAHEN AKELYAN
Issued 6/23/2022 APPLICANT
CofO in Progress 1/9/2023 WILLIAM WREN
Permit Finaled 1/14/2023 MICHAEL SMITH
CofO Issued 1/14/2023 MICHAEL SMITH
Permit Finaled 1/14/2023 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/8/2022 GEORGE ALVAREZ
Address approval Cleared 4/14/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/14/2022 JOSE DUARTE-DIAZ
Miscellaneous Cleared 4/14/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 4/14/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/14/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 5/17/2022 RIDWAN HARDY
Construction within easement Cleared 5/17/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/19/2022 Partial Approval WILLIAM WREN
Excavation/Setback/Form/Re-Bar 7/25/2022 Approved MATTHEW NELSON
Footing/Foundation/Slab 7/25/2022 Approved MATTHEW NELSON
Sewer 7/25/2022 Approved MATTHEW NELSON
Underground Mechanical 7/25/2022 Approved MATTHEW NELSON
Deputy Drilled-In Anchors 8/3/2022 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 8/10/2022 Partial Approval MATTHEW NELSON
Green Building Rough 8/10/2022 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 8/17/2022 Partial Approval MATTHEW NELSON
PLUMBING-Rough 8/17/2022 Approved MATTHEW NELSON
Green Building Rough 8/24/2022 Approved MATTHEW NELSON
HVAC-Rough 8/24/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/29/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/6/2022 Approved MATTHEW NELSON
Insulation 9/6/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/6/2022 Approved MATTHEW NELSON
Drywall Nailing 9/22/2022 Approved MATTHEW NELSON
Shower Pan 9/27/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/30/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Not Ready WILLIAM WREN
Underground Mechanical 11/23/2022 Approved WILLIAM WREN
ELECTRICAL-Final 12/5/2022 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 12/5/2022 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 12/5/2022 SGSOV Approved WILLIAM WREN
Final 12/15/2022 Corrections Issued WILLIAM WREN
Green Building Final 12/15/2022 Approved WILLIAM WREN
Smoke Detectors 12/15/2022 Approved WILLIAM WREN
Final 1/5/2023 OK to Issue CofO WILLIAM WREN