1271 N SUNSET PLAZA DR 90069

Certificate Information: 1271 N SUNSET PLAZA DR 90069

Application / Permit
22014-10000-01402
Plan Check / Job No.
B22LA05289
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SINGLE FAMILY DWELLING W/ATT GARAGE
Permit Issued
Issued on 5/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 LAMAR DAVIS
Corrections Issued 4/4/2022 LAMAR DAVIS
Quality Review Completed 4/19/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 4/21/2022 APPLICANT
Applicant returned to address corrections 7/29/2022 LAMAR DAVIS
Plan Check Approved 10/19/2022 LAMAR DAVIS
Issued 5/17/2023 APPLICANT
CofO in Progress 5/15/2025 BRIAN SULLIVAN
Permit Finaled 5/17/2025 DEROLD HAUFF
CofO Issued 5/17/2025 DEROLD HAUFF
Permit Finaled 5/17/2025 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 4/2/2022 ALEXANDER HELFER
Grading Pre-Inspection Cleared 4/2/2022 ALEXANDER HELFER
BHO/Hillside ordinance Cleared 4/7/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 4/7/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 4/7/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 4/7/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 4/8/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 4/8/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 5/3/2022 JEANETTE VONG
Hydrant and Access approval Cleared 5/5/2022 LAURINDA MEADE
Roof/Waste drainage to street Cleared 9/7/2022 THAN WIN
Miscellaneous Cleared 10/13/2022 ALBERT TAM

Contact Information

Contractor Owner-Builder       ,
Engineer Abedian,, Vanik; Lic. No.: S5323 2906 JOLLEY DR      BURBANK, CA 91504
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/25/2023 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/30/2023 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/30/2023 Not Ready for Inspection RAUL BARAJAS
Pre-Inspection 5/30/2023 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/6/2023 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/28/2023 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 6/28/2023 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/3/2023 Approved RAUL BARAJAS
Green Building Rough 7/12/2023 Not Ready for Inspection RAUL BARAJAS
Structural Steel Frame 7/12/2023 Approved RAUL BARAJAS
Wood Frame 7/12/2023 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 7/13/2023 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 7/19/2023 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Inspection RAUL BARAJAS
Deputy Wood Construction 8/11/2023 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Approved RAUL BARAJAS
PLUMBING-Rough 9/14/2023 Approved RAUL BARAJAS
Deputy Drilled-In Anchors 9/29/2023 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 10/2/2023 Conditional Approval JUSTIN HAWLEY
HVAC-Rough 10/30/2023 Corrections Issued RONNIE MINDANAO
HVAC-Rough 11/13/2023 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 11/15/2023 Not Ready for Inspection RAUL BARAJAS
Masonry Wall/Backfill 11/15/2023 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 11/28/2023 Approved RAUL BARAJAS
ELECTRICAL-Rough 12/21/2023 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 12/21/2023 Approved RAUL BARAJAS
Shower Pan 12/21/2023 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 12/28/2023 Approved RAUL BARAJAS
Insulation 12/29/2023 Not Ready for Inspection RAUL BARAJAS
Shower Pan 12/29/2023 Approved RAUL BARAJAS
Insulation 1/4/2024 Approved RAUL BARAJAS
Service/Power Release 1/16/2024 Not Ready for Inspection RAUL BARAJAS
Drywall Nailing 1/19/2024 Approved RAUL BARAJAS
Green Building Rough 1/19/2024 Approved RAUL BARAJAS
Service/Power Release 1/19/2024 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 1/31/2024 Corrections Issued RAUL BARAJAS
ELECTRICAL-Final 9/9/2024 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 9/9/2024 Corrections Issued HAMIK HARTOUNIAN
Service/Power Release 9/9/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 9/16/2024 Corrections Issued RAUL BARAJAS
HVAC-Final 9/16/2024 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 9/20/2024 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 9/25/2024 Approved RAUL BARAJAS
ELECTRICAL-Final 11/1/2024 Approved RAUL BARAJAS
Final 11/1/2024 Corrections Issued RAUL BARAJAS
HVAC-Final 11/1/2024 Approved RAUL BARAJAS
Verify Rec and Parks Fee Memo 11/1/2024 Approved RAUL BARAJAS
BUILDING-Rough-Frame 4/28/2025 Not Ready for Inspection ROY SPAULDING
Final 4/28/2025 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 4/28/2025 Not Ready for Inspection ROY SPAULDING
Green Building Final 4/28/2025 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 4/28/2025 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 5/1/2025 Not Ready for Inspection BRIAN SULLIVAN
Final 5/1/2025 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 5/1/2025 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 5/1/2025 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 5/1/2025 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 5/1/2025 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 5/9/2025 Approved ROY SPAULDING
Final 5/9/2025 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 5/9/2025 Approved ROY SPAULDING
Green Building Final 5/9/2025 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 5/9/2025 Approved ROY SPAULDING
Final 5/14/2025 OK to Issue CofO BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved BRIAN SULLIVAN