442 W 68TH ST 90003
Certificate Information: 442 W 68TH ST 90003
- Application / Permit
- 22014-10000-01389
- Plan Check / Job No.
- B22LA05241
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) GARAGE AND CONVERT INTO (N) ADU PER ORDINANCE AND LAMC 12.22 A33 (c) &(d). All work done per WFPP
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Current Status
- CofO Issued on 11/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2022 | ZAW HAN |
| Corrections Issued | 4/11/2022 | ZAW HAN |
| Plan Check Approved | 4/21/2022 | KHUONG TRUONG |
| Issued | 5/2/2022 | APPLICANT |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| CofO in Progress | 10/27/2022 | LILIANA PORTILLO |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
| CofO Issued | 11/5/2022 | DEROLD HAUFF |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 4/16/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/18/2022 | JEANETTE VONG |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/7/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 6/13/2022 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/16/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/20/2022 | Partial Approval | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 6/24/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/24/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 7/19/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/1/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/1/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 8/1/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 8/1/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/5/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/5/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 8/5/2022 | Approved | LILIANA PORTILLO |
| Insulation | 8/8/2022 | Conditional Approval | LILIANA PORTILLO |
| Drywall Nailing | 8/18/2022 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 8/18/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/18/2022 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 8/18/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/24/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/27/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/27/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/27/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 9/27/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Gas Test | 9/27/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 9/27/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 9/27/2022 | Corrections Issued | LILIANA PORTILLO |
| MERV13>=Final | 9/27/2022 | Approved | LILIANA PORTILLO |
| MERV13>=Rough | 9/27/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 9/27/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 9/27/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 9/27/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 10/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 10/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 10/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 10/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Sewer | 10/6/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 10/6/2022 | Approved | LILIANA PORTILLO |
| Final | 10/14/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 10/14/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/19/2022 | Approved | LILIANA PORTILLO |
| Final | 10/19/2022 | Conditional Approval | LILIANA PORTILLO |
| Green Building Final | 10/19/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 10/19/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 10/19/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/19/2022 | SGSOV Approved | LILIANA PORTILLO |