1202 N COMMONWEALTH AVE 90029

Certificate Information: 1202 N COMMONWEALTH AVE 90029

Application / Permit
22014-10000-01383
Plan Check / Job No.
B22LA05216
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND FLOOR ADDITION AND INTERIOR/EXTERIOR REMODEL TO EXISTING ONE STORY SFD
Permit Issued
Issued on 1/6/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 STARR CHEN
Corrections Issued 4/14/2022 STARR CHEN
Quality Review Completed 4/20/2022 KEN GILL
Building Plans Picked Up 4/25/2022 APPLICANT
Plan Check Approved 7/13/2022 STARR CHEN
Issued 1/6/2023 APPLICANT
CofO in Progress 7/12/2024 FREDDIE RIVERA
Permit Finaled 7/29/2024 DEROLD HAUFF
CofO Issued 7/29/2024 DEROLD HAUFF
Permit Finaled 7/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 4/28/2022 CINDY QI
Roof/Waste drainage to street Cleared 4/28/2022 CINDY QI
Sewer availability Cleared 4/28/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 5/2/2022 CINDY QI
Grading Pre-Inspection Cleared 6/8/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/24/2023 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 1/24/2023 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 2/7/2023 Approved FREDDIE RIVERA
Reinforced Concrete Frame 2/7/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/9/2023 Partial Approval FREDDIE RIVERA
Insulation 2/9/2023 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 2/9/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 3/31/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 3/31/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 3/31/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/27/2023 Conditional Approval FREDDIE RIVERA
Green Building Rough 4/27/2023 Partial Inspection FREDDIE RIVERA
Interior/Exterior Lathing 4/27/2023 Partial Inspection FREDDIE RIVERA
Insulation 5/8/2023 Approved FREDDIE RIVERA
Drywall Nailing 6/1/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 6/1/2023 Approved FREDDIE RIVERA
Wood Frame 6/1/2023 Approved FREDDIE RIVERA
Footing/Foundation/Slab 6/28/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 5/30/2024 Approved FREDDIE RIVERA
ELECTRICAL-Final 5/30/2024 Corrections Issued FREDDIE RIVERA
Final 5/30/2024 Corrections Issued FREDDIE RIVERA
Green Building Final 5/30/2024 Approved FREDDIE RIVERA
Green Building Rough 5/30/2024 Approved FREDDIE RIVERA
HVAC-Final 5/30/2024 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 5/30/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/30/2024 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 5/30/2024 Partial Inspection FREDDIE RIVERA
Smoke Detectors 5/30/2024 Approved FREDDIE RIVERA
Final 7/10/2024 OK to Issue CofO FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/10/2024 SGSOV Approved FREDDIE RIVERA