14304 W MIRANDA ST 91401
Certificate Information: 14304 W MIRANDA ST 91401
- Application / Permit
- 22014-10000-01375
- Plan Check / Job No.
- B22LA05201
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE WITH NEW ADDITION INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/23/2022
- Issuing Office
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | KEVIN MORALES |
| Corrections Issued | 4/21/2022 | KEVIN MORALES |
| Plan Check Approved | 5/11/2022 | KEVIN MORALES |
| Issued | 5/23/2022 | APPLICANT |
| CofO in Progress | 11/30/2022 | RYAN SALAZAR |
| CofO Issued | 12/10/2022 | MICHAEL SMITH |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/5/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 5/5/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/5/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Better Together Builders Inc; Lic. No.: 1047689-B | , |
| Engineer | Dominguez,, Refugio; Lic. No.: NA50820 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/10/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 6/28/2022 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 7/6/2022 | Corrections Issued | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 7/27/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Partial Approval | JENNIFER RABUCHIN |
| Gas Test | 7/27/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/27/2022 | Approved | JENNIFER RABUCHIN |
| Sewer | 7/27/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 7/27/2022 | Approved | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 7/28/2022 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/24/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 8/24/2022 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 8/24/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/24/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 8/24/2022 | Corrections Issued | RAUL OLAGI |
| Shower Pan | 8/24/2022 | Approved | RAUL OLAGI |
| Insulation | 8/30/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/30/2022 | Approved | WILLIAM WREN |
| Pre-Inspection | 8/30/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/7/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 11/16/2022 | Approved | RICHARD DOCKUS |
| Final | 11/16/2022 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 11/16/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 11/16/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 11/16/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 11/16/2022 | Approved | RICHARD DOCKUS |
| Final | 11/29/2022 | OK to Issue CofO | RYAN SALAZAR |