4369 W ROSEWOOD AVE 90004

Certificate Information: 4369 W ROSEWOOD AVE 90004

Application / Permit
22014-10000-01373
Plan Check / Job No.
B22LA05199
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. NEW 2-STORY ACCESSORY DWELLING ADDITION OVER (E) DETACHED GARAGE PER LAMC 12.22 A.33 (c)-(d). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit."
Permit Issued
Issued on 8/22/2022
Issuing Office
Current Status
CofO Issued on 12/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 KEVIN MORALES
Corrections Issued 4/11/2022 KEVIN MORALES
Quality Review Completed 4/13/2022 EUGENE BARBEAU
Applicant returned to address corrections 7/12/2022 KEVIN MORALES
Plan Check Approved 7/22/2022 KEVIN MORALES
Issued 8/22/2022 APPLICANT
CofO in Progress 12/9/2025 LUIS CCAMACHO
Permit Finaled 12/9/2025 ERNESTO CORRAL
CofO Issued 12/9/2025 ERNESTO CORRAL
Permit Finaled 12/9/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 5/6/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/25/2022 CELINA MORENO
Sewer availability Cleared 5/25/2022 CELINA MORENO
Construction near power lines Cleared 6/13/2022 TINA MIRANDA
Roof/Waste drainage to street Cleared 7/20/2022 CELINA MORENO

Contact Information

Architect Bruce,, Thomas A; Lic. No.: NA31251       ,
Contractor Fgc Construction Inc; Lic. No.: 920242-B       ,
Engineer Garza,, Omar Leonel; Lic. No.: NA5593       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/27/2022 Approved DAVID BURKHEAD
Footing/Foundation/Slab 3/31/2023 Approved RONALD JIMENEZ
Deputy Other (see comments) 5/12/2023 Conditional Approval RONALD JIMENEZ
Deputy Reinf. Masonry 5/12/2023 Conditional Approval RONALD JIMENEZ
Masonry Wall/Backfill 5/12/2023 Partial Approval RONALD JIMENEZ
Masonry Wall/Backfill 5/15/2023 No Access for Inspection RONALD JIMENEZ
Masonry Wall/Backfill 6/9/2023 Partial Approval RAMAZANALI ALMASI
Masonry Wall/Backfill 6/12/2023 Partial Inspection RONALD JIMENEZ
Deputy Reinf. Masonry 6/13/2023 Conditional Approval MICHAEL ROSENBERG
Grading Pre-Inspection 7/24/2023 Not Ready for Inspection VAHE KELEDJIAN
Excavation/Setback/Form/Re-Bar 7/28/2023 Approved RONALD JIMENEZ
Footing/Foundation/Slab 7/28/2023 Approved RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 8/10/2023 Conditional Approval RONALD JIMENEZ
Deputy Drilled-In Anchors 11/6/2023 Conditional Approval RONALD JIMENEZ
Deputy Wood Construction 11/27/2023 Conditional Approval RONALD JIMENEZ
Deputy Drilled-In Anchors 12/7/2023 Conditional Approval RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Partial Approval LUIS CCAMACHO
Green Building Rough 2/13/2024 Not Ready for Inspection LUIS CCAMACHO
Wood Frame 2/13/2024 Partial Approval LUIS CCAMACHO
Green Building Rough 5/9/2024 Not Ready for Inspection RAFAEL CORTES
Interior/Exterior Lathing 5/9/2024 Not Ready for Inspection RAFAEL CORTES
Wood Frame 5/9/2024 Not Ready for Inspection RAFAEL CORTES
Interior/Exterior Lathing 5/10/2024 Partial Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Not Ready TIMOTHY POWELL
Special/Order Compliance 5/10/2024 Not Ready for Inspection TIMOTHY POWELL
Interior/Exterior Lathing 5/16/2024 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 5/16/2024 Partial Inspection TIMOTHY POWELL
Special/Order Compliance 5/17/2024 Corrections Issued TIMOTHY POWELL
Green Building Rough 6/5/2024 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 6/5/2024 Not Ready for Inspection TIMOTHY POWELL
Green Building Rough 6/12/2024 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 6/12/2024 Partial Approval TIMOTHY POWELL
Insulation 6/20/2024 Approved RAMAZANALI ALMASI
Special/Order Compliance 6/20/2024 Partial Inspection RAMAZANALI ALMASI
Interior/Exterior Lathing 7/3/2024 Not Ready for Inspection RAMAZANALI ALMASI
Interior/Exterior Lathing 7/8/2024 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 7/12/2024 Partial Approval TIMOTHY POWELL
Green Building Rough 7/12/2024 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 7/17/2024 Partial Approval TIMOTHY POWELL
Green Building Rough 7/17/2024 Not Ready for Inspection TIMOTHY POWELL
Interior/Exterior Lathing 7/23/2024 Not Ready for Inspection TIMOTHY POWELL
Interior/Exterior Lathing 7/26/2024 Corrections Issued TIMOTHY POWELL
Interior/Exterior Lathing 7/29/2024 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 8/13/2024 Approved TIMOTHY POWELL
Drywall Nailing 10/20/2025 Partial Inspection TIMOTHY POWELL
Final 10/20/2025 Partial Inspection TIMOTHY POWELL
Green Building Final 10/20/2025 Not Ready for Inspection TIMOTHY POWELL
Green Building Rough 10/20/2025 Not Ready for Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 10/20/2025 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 10/20/2025 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 10/20/2025 Partial Approval TIMOTHY POWELL
Drywall Nailing 10/31/2025 Approved LUIS CCAMACHO
Final 10/31/2025 OK to Issue CofO LUIS CCAMACHO
Green Building Final 10/31/2025 Approved LUIS CCAMACHO
Green Building Rough 10/31/2025 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 10/31/2025 Approved LUIS CCAMACHO
Wood Frame 10/31/2025 Approved LUIS CCAMACHO