4369 W ROSEWOOD AVE 90004
Certificate Information: 4369 W ROSEWOOD AVE 90004
- Application / Permit
- 22014-10000-01373
- Plan Check / Job No.
- B22LA05199
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW 2-STORY ACCESSORY DWELLING ADDITION OVER (E) DETACHED GARAGE PER LAMC 12.22 A.33 (c)-(d). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit."
- Permit Issued
- Issued on 8/22/2022
- Issuing Office
- Current Status
- CofO Issued on 12/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | KEVIN MORALES |
| Corrections Issued | 4/11/2022 | KEVIN MORALES |
| Quality Review Completed | 4/13/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/12/2022 | KEVIN MORALES |
| Plan Check Approved | 7/22/2022 | KEVIN MORALES |
| Issued | 8/22/2022 | APPLICANT |
| CofO in Progress | 12/9/2025 | LUIS CCAMACHO |
| Permit Finaled | 12/9/2025 | ERNESTO CORRAL |
| CofO Issued | 12/9/2025 | ERNESTO CORRAL |
| Permit Finaled | 12/9/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2022 | CELINA MORENO |
| Sewer availability | Cleared | 5/25/2022 | CELINA MORENO |
| Construction near power lines | Cleared | 6/13/2022 | TINA MIRANDA |
| Roof/Waste drainage to street | Cleared | 7/20/2022 | CELINA MORENO |
Contact Information
| Architect | Bruce,, Thomas A; Lic. No.: NA31251 | , |
| Contractor | Fgc Construction Inc; Lic. No.: 920242-B | , |
| Engineer | Garza,, Omar Leonel; Lic. No.: NA5593 | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/27/2022 | Approved | DAVID BURKHEAD |
| Footing/Foundation/Slab | 3/31/2023 | Approved | RONALD JIMENEZ |
| Deputy Other (see comments) | 5/12/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Reinf. Masonry | 5/12/2023 | Conditional Approval | RONALD JIMENEZ |
| Masonry Wall/Backfill | 5/12/2023 | Partial Approval | RONALD JIMENEZ |
| Masonry Wall/Backfill | 5/15/2023 | No Access for Inspection | RONALD JIMENEZ |
| Masonry Wall/Backfill | 6/9/2023 | Partial Approval | RAMAZANALI ALMASI |
| Masonry Wall/Backfill | 6/12/2023 | Partial Inspection | RONALD JIMENEZ |
| Deputy Reinf. Masonry | 6/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Grading Pre-Inspection | 7/24/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Excavation/Setback/Form/Re-Bar | 7/28/2023 | Approved | RONALD JIMENEZ |
| Footing/Foundation/Slab | 7/28/2023 | Approved | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 8/10/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Drilled-In Anchors | 11/6/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Wood Construction | 11/27/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Drilled-In Anchors | 12/7/2023 | Conditional Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Partial Approval | LUIS CCAMACHO |
| Green Building Rough | 2/13/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Wood Frame | 2/13/2024 | Partial Approval | LUIS CCAMACHO |
| Green Building Rough | 5/9/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Interior/Exterior Lathing | 5/9/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 5/9/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Interior/Exterior Lathing | 5/10/2024 | Partial Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Not Ready | TIMOTHY POWELL |
| Special/Order Compliance | 5/10/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Interior/Exterior Lathing | 5/16/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 5/16/2024 | Partial Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 5/17/2024 | Corrections Issued | TIMOTHY POWELL |
| Green Building Rough | 6/5/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 6/5/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Green Building Rough | 6/12/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 6/12/2024 | Partial Approval | TIMOTHY POWELL |
| Insulation | 6/20/2024 | Approved | RAMAZANALI ALMASI |
| Special/Order Compliance | 6/20/2024 | Partial Inspection | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 7/3/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 7/8/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 7/12/2024 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 7/12/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 7/17/2024 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 7/17/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Interior/Exterior Lathing | 7/23/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Interior/Exterior Lathing | 7/26/2024 | Corrections Issued | TIMOTHY POWELL |
| Interior/Exterior Lathing | 7/29/2024 | Partial Approval | RONALD JIMENEZ |
| Interior/Exterior Lathing | 8/13/2024 | Approved | TIMOTHY POWELL |
| Drywall Nailing | 10/20/2025 | Partial Inspection | TIMOTHY POWELL |
| Final | 10/20/2025 | Partial Inspection | TIMOTHY POWELL |
| Green Building Final | 10/20/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Green Building Rough | 10/20/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 10/20/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 10/20/2025 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 10/31/2025 | Approved | LUIS CCAMACHO |
| Final | 10/31/2025 | OK to Issue CofO | LUIS CCAMACHO |
| Green Building Final | 10/31/2025 | Approved | LUIS CCAMACHO |
| Green Building Rough | 10/31/2025 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 10/31/2025 | Approved | LUIS CCAMACHO |
| Wood Frame | 10/31/2025 | Approved | LUIS CCAMACHO |