731 N LAUREL AVE 90046

Certificate Information: 731 N LAUREL AVE 90046

Application / Permit
22014-10000-01355
Plan Check / Job No.
B22LA05124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND INTERIOR REMODEL TO (E) SFD
Permit Issued
Issued on 9/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2022 APPLICANT
Assigned to Plan Check Engineer 6/27/2022 ZAW HAN
Corrections Issued 6/29/2022 ZAW HAN
Building Plans Picked Up 7/19/2022 APPLICANT
Plan Check Approved 9/7/2022 FERNANDO FLORES
Issued 9/7/2022 APPLICANT
CofO in Progress 3/9/2026 JOSH MEISTER
Permit Finaled 3/10/2026 DEROLD HAUFF
CofO Issued 3/10/2026 DEROLD HAUFF
Permit Finaled 3/10/2026 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 8/29/2022 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 8/31/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 8/31/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 8/31/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/2/2023 Conditional Approval MICHAEL LEWIS
Footing/Foundation/Slab 4/24/2023 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 8/4/2023 Partial Approval SCOTT FINNILA
Pre-Inspection 8/29/2023 Partial Inspection LILIANA PORTILLO
ELECTRICAL-Rough 9/13/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 9/13/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 9/13/2023 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 9/18/2023 Partial Approval LILIANA PORTILLO
Insulation 9/26/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/26/2023 Partial Approval LILIANA PORTILLO
Drywall Nailing 11/9/2023 Partial Approval LILIANA PORTILLO
Green Building Rough 11/9/2023 Partial Approval LILIANA PORTILLO
Shower Pan 12/6/2023 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 4/10/2024 Partial Approval AMIR NAZARIAN
Drywall Nailing 4/10/2024 Partial Approval AMIR NAZARIAN
Final 4/10/2024 Not Ready for Inspection AMIR NAZARIAN
Green Building Final 4/10/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 4/10/2024 Corrections Issued AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved AMIR NAZARIAN
Smoke Detectors 4/10/2024 Corrections Issued AMIR NAZARIAN
Insulation 4/19/2024 Not Ready for Inspection AMIR NAZARIAN
BUILDING-Rough-Frame 8/22/2024 Corrections Issued AMIR NAZARIAN
Drywall Nailing 8/22/2024 Corrections Issued AMIR NAZARIAN
Final 8/22/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 8/22/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 8/22/2024 Corrections Issued AMIR NAZARIAN
Smoke Detectors 8/22/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 1/29/2026 Approved JOSH MEISTER
Drywall Nailing 1/29/2026 Approved JOSH MEISTER
Final 1/29/2026 Corrections Issued JOSH MEISTER
Green Building Final 1/29/2026 Not Ready for Inspection JOSH MEISTER
Green Building Rough 1/29/2026 Approved JOSH MEISTER
Smoke Detectors 1/29/2026 Approved JOSH MEISTER
Final 2/18/2026 Corrections Issued JOSH MEISTER
Green Building Final 2/18/2026 Not Ready for Inspection JOSH MEISTER
Final 2/24/2026 No Access for Inspection ENRIQUE MIRELES
Green Building Final 2/24/2026 No Access for Inspection ENRIQUE MIRELES
Final 3/3/2026 OK to Issue CofO JOSH MEISTER
Green Building Final 3/3/2026 Approved JOSH MEISTER