10511 N ONEIDA AVE 91331

Certificate Information: 10511 N ONEIDA AVE 91331

Application / Permit
22014-10000-01354
Plan Check / Job No.
B22LA05117
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSATION OF (E) DETACHED GARAGE TO (N) ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 11/14/2022
Issuing Office
Current Status
CofO Issued on 6/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 4/4/2022 FERNANDO FLORES
Corrections Issued 4/5/2022 FERNANDO FLORES
Building Plans Picked Up 4/12/2022 APPLICANT
Applicant returned to address corrections 5/6/2022 MINA HABILI
Plan Check Approved 5/23/2022 SHANGQIN XIE
Issued 11/14/2022 APPLICANT
CofO in Progress 6/27/2023 MICHEL ABAJAN
Permit Finaled 6/29/2023 MICHAEL SMITH
CofO Issued 6/29/2023 MICHAEL SMITH
Permit Finaled 6/29/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/19/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 4/19/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/26/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 4/26/2022 DAGOVERTO GUERRERO

Contact Information

Architect Song,, Michael; Lic. No.: C32566 821 LIME AVENUE      LONG BEACH, CA 90813
Contractor L E H Creations; Lic. No.: 898567-B 10395 ONEIDA AVE      PACOIMA, CA 91331
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/30/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 11/30/2022 Approved MICHEL ABAJAN
Gas Test 11/30/2022 Approved MICHEL ABAJAN
METHANE-Barrier 11/30/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 11/30/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 11/30/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 11/30/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/24/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 1/24/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 1/24/2023 Corrections Issued JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 1/24/2023 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 1/24/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 2/2/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/2/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 2/2/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/3/2023 Approved MICHEL ABAJAN
Green Building Rough 2/3/2023 Approved MICHEL ABAJAN
METHANE-Rough 2/3/2023 Approved MICHEL ABAJAN
Insulation 2/8/2023 Approved MICHEL ABAJAN
Drywall Nailing 2/17/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/7/2023 Corrections Issued MICHEL ABAJAN
Final 6/7/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 6/7/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 6/7/2023 Approved MICHEL ABAJAN
PLUMBING-Final 6/7/2023 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 6/7/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/26/2023 Approved MICHEL ABAJAN
Final 6/26/2023 OK to Issue CofO MICHEL ABAJAN
Green Building Final 6/26/2023 Approved MICHEL ABAJAN
PLUMBING-Final 6/26/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Approved MICHEL ABAJAN