12040 N DARBY AVE 91326

Certificate Information: 12040 N DARBY AVE 91326

Application / Permit
22014-10000-01343
Plan Check / Job No.
B22LA05072
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1ST AND 2ND FLOOR ADDITION TO AN EXISTING SINGLE FAMILY DWELLING WITH AN ATTACHED GARAGE.
Permit Issued
Issued on 6/22/2022
Issuing Office
Current Status
Issued on 6/22/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/22/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 KEVIN MORALES
Corrections Issued 4/8/2022 KEVIN MORALES
Quality Review Completed 4/12/2022 EUGENE BARBEAU
Building Plans Picked Up 4/14/2022 APPLICANT
Applicant returned to address corrections 6/15/2022 KEVIN MORALES
Plan Check Approved 6/22/2022 KEVIN MORALES
Issued 6/22/2022 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/27/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 4/27/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 4/27/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 4/27/2022 CARLOS AGUILERA
Distance to fire station Cleared 5/13/2022 KURT CORRAL
Hydrant and Access approval Cleared 5/13/2022 KURT CORRAL
Low Impact Development Cleared 6/2/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 6/6/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/7/2022 CARLOS AGUILERA
Low Impact Development Cleared 6/7/2022 SARAH YOUSSEF
Sewer availability Cleared 6/7/2022 CARLOS AGUILERA
GPI Written Notices Cleared 6/15/2022 KEVIN MORALES
Grading Pre-Inspection Cleared 6/15/2022 KEVIN MORALES

Contact Information

Contractor Owner-Builder       ,
Engineer Basso,, Alexandre; Lic. No.: C77670 7231 SUMMITROSE ST      TUJUNGA, CA 91042

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/21/2022 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 9/26/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Partial Approval JOHN KIDWELL
HVAC-Rough 4/5/2023 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 4/25/2023 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 4/25/2023 Corrections Issued STEVEN BACK
PLUMBING-Rough 4/25/2023 Approved STEVEN BACK
HVAC-Rough 4/26/2023 Approved STEVEN BACK
Deputy Wood Construction 5/23/2023 Conditional Approval STEVEN BACK
BUILDING-Rough-Frame 5/25/2023 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 5/25/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Corrections Issued STEVEN BACK
Green Building Rough 5/25/2023 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 10/16/2023 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Approved STEVEN BACK
Green Building Rough 10/16/2023 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 12/29/2023 Approved STEVEN BACK
Green Building Rough 12/29/2023 Approved STEVEN BACK
Insulation 12/29/2023 Approved STEVEN BACK
Interior/Exterior Lathing 12/29/2023 Partial Approval STEVEN BACK
Drywall Nailing 2/29/2024 Approved STEVEN BACK
Shower Pan 4/9/2024 Corrections Issued HENRY KIM
Interior/Exterior Lathing 4/29/2024 Approved JEFFREY PARD
Shower Pan 4/29/2024 Approved JEFFREY PARD
Final 5/20/2025 Corrections Issued STEVEN BACK
Green Building Final 5/20/2025 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Approved STEVEN BACK
Smoke Detectors 5/20/2025 Approved STEVEN BACK