332 1/2 S DETROIT ST 90036
Certificate Information: 332 1/2 S DETROIT ST 90036
- Application / Permit
- 22014-10000-01327
- Plan Check / Job No.
- B22LA05038
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2ND STORY A.D.U ADDITION TO DETACHED GARAGE. ALL TO APARTMENT HOUSE
- Permit Issued
- Issued on 2/2/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | NGHI SU |
| Corrections Issued | 4/27/2022 | NGHI SU |
| Quality Review Completed | 5/4/2022 | KEN GILL |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| Applicant returned to address corrections | 6/24/2022 | NGHI SU |
| Green Plans Picked Up | 8/8/2022 | APPLICANT |
| Plan Check Approved | 9/16/2022 | NGHI SU |
| Issued | 2/2/2023 | APPLICANT |
| CofO in Progress | 11/1/2023 | RICHARD DOCKUS |
| Permit Finaled | 11/3/2023 | DEROLD HAUFF |
| CofO Issued | 11/3/2023 | DEROLD HAUFF |
| Permit Finaled | 11/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/23/2022 | MICHAEL SOTO |
| "Q" conditions | Cleared | 5/24/2022 | KENTON TRINH |
| Roof/Waste drainage to street | Cleared | 5/26/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/14/2022 | STEVE MELGAR |
| Address approval | Cleared | 6/15/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 9/9/2022 | RIDWAN HARDY |
Contact Information
| Architect | Besbelli,, San Ragip; Lic. No.: C28069 | 564 WEST 3RD STREET SAN PEDRO, CA 90731 |
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/21/2023 | No Access for Inspection | JOSEPH MCGARRY |
| METHANE-Subgrade | 4/21/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Special/Order Compliance | 4/25/2023 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/28/2023 | Corrections Issued | JEROME BLACKWOOD |
| Pre-Inspection | 5/1/2023 | Not Ready for Inspection | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Corrections Issued | SCOTT FINNILA |
| METHANE-Barrier | 5/8/2023 | Partial Approval | RICHARD DOCKUS |
| Wood Frame | 6/9/2023 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 7/19/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 7/19/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 7/24/2023 | Approved | SCOTT FINNILA |
| METHANE-Barrier | 7/24/2023 | Approved | SCOTT FINNILA |
| METHANE-Subgrade | 7/24/2023 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 7/24/2023 | Approved | SCOTT FINNILA |
| Wood Frame | 7/26/2023 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/4/2023 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/4/2023 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Rough | 8/4/2023 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 8/4/2023 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 8/8/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 8/14/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/14/2023 | Approved | JOSEPH MCGARRY |
| Shower Pan | 8/14/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 10/3/2023 | Approved | RICHARD DOCKUS |
| Green Building Final | 10/3/2023 | Approved | RICHARD DOCKUS |
| HVAC-Final | 10/3/2023 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Final | 10/3/2023 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 10/3/2023 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 10/3/2023 | Approved | RICHARD DOCKUS |
| Gas Test | 10/13/2023 | Approved | RICHARD DOCKUS |
| Final | 10/23/2023 | Corrections Issued | RICHARD DOCKUS |
| Final | 11/1/2023 | OK to Issue CofO | RICHARD DOCKUS |