19051 W ARMINTA ST 91335
Certificate Information: 19051 W ARMINTA ST 91335
- Application / Permit
- 22014-10000-01322
- Plan Check / Job No.
- B22LA04992
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 STORY ADDITION AND MAJOR REMODEL TO EXISTING 1 STORY SINGLE FAMILY DWELLING. REFRAME ENTIRE ROOF.
- Permit Issued
- Issued on 12/22/2022
- Issuing Office
- Valley
- Current Status
- Issued on 12/22/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | ADRIANA LOPEZ |
| Corrections Issued | 5/7/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 5/13/2022 | FARUK SEZER |
| Plan Check Approved | 12/22/2022 | ADRIANA LOPEZ |
| Issued | 12/22/2022 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/13/2022 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | MEGAN GODINEZ |
| Miscellaneous | Cleared | 6/14/2022 | YINGSHI HUANG |
| Roof/Waste drainage to street | Cleared | 6/14/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/14/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/14/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/14/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/14/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Rigo'S Construction Inc; Lic. No.: 853575-B | P O BOX 922918 SYLMAR, CA 913922918 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/27/2022 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 12/27/2022 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 1/18/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 3/7/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 3/7/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 3/7/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 3/20/2023 | Approved | SEAN HAUPT |
| Special/Order Compliance | 3/20/2023 | Corrections Issued | SEAN HAUPT |
| Insulation | 5/17/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 5/19/2023 | Not Ready for Inspection | JEFFREY BULL |
| Drywall Nailing | 5/24/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 7/27/2023 | Approved | JUSTIN HAWLEY |
| Shower Pan | 7/27/2023 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | JEFFREY BULL |
| Final | 1/29/2024 | Corrections Issued | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 1/29/2024 | Not Ready for Inspection | JEFFREY BULL |