2240 N DORRIS PL 90031
Certificate Information: 2240 N DORRIS PL 90031
- Application / Permit
- 22014-10000-01309
- Plan Check / Job No.
- B22LA04968
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERSION OF (E) GARAGE INTO A.D.U. PER STATE LAW. 1 OF 2
- Permit Issued
- Issued on 7/1/2022
- Issuing Office
- Current Status
- CofO Issued on 6/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 4/2/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Plan Check Approved | 7/1/2022 | JOSEPH RAFOLS |
| Issued | 7/1/2022 | APPLICANT |
| CofO in Progress | 6/13/2023 | THOMAS LOGRASSO |
| Permit Finaled | 6/27/2023 | DEROLD HAUFF |
| CofO Issued | 6/27/2023 | DEROLD HAUFF |
| Permit Finaled | 6/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Supp. Use District POD/CDO/TDO | Cleared | 4/14/2022 | YINGSHI HUANG |
| Address approval | Cleared | 4/18/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 4/19/2022 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 5/9/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 6/15/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 6/17/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/15/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/15/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 8/22/2022 | Approved | RUBEN SALAS |
| Footing/Foundation/Slab | 8/22/2022 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 10/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 10/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 10/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 11/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 11/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 11/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/15/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 11/15/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 11/15/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 11/15/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 11/15/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/15/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Wood Construction | 11/17/2022 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 11/21/2022 | Approved | DONALD CRICHLOW |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Approved | DONALD CRICHLOW |
| PLUMBING-Rough | 11/21/2022 | Approved | DONALD CRICHLOW |
| Underground Mechanical | 11/21/2022 | Approved | DONALD CRICHLOW |
| HVAC-Rough | 11/28/2022 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 11/28/2022 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/30/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 11/30/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 11/30/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 11/30/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/30/2022 | Partial Approval | THOMAS LOGRASSO |
| MERV13>=Rough | 11/30/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 12/9/2022 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/29/2022 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 1/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/6/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 2/24/2023 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 2/24/2023 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 2/24/2023 | Partial Approval | STUART CHAPMAN |
| Final | 5/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/1/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 5/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 5/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 5/1/2023 | Approved | THOMAS LOGRASSO |
| Final | 5/11/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 5/11/2023 | Approved | THOMAS LOGRASSO |
| MERV13>=Final | 5/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 6/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 6/1/2023 | Approved | THOMAS LOGRASSO |
| Final | 6/12/2023 | OK to Issue CofO | THOMAS LOGRASSO |