5663 W SPOKANE ST 90016
Certificate Information: 5663 W SPOKANE ST 90016
- Application / Permit
- 22014-10000-01299
- Plan Check / Job No.
- B22LA04937
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) 1-STORY SFD 1 OF 2
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | KHUONG TRUONG |
| Corrections Issued | 4/2/2022 | KHUONG TRUONG |
| Plan Check Approved | 11/4/2022 | FERNANDO FLORES |
| Issued | 12/16/2022 | APPLICANT |
| CofO in Progress | 8/16/2024 | ARTHUR NEGRETE |
| Permit Finaled | 3/30/2025 | DEROLD HAUFF |
| CofO Issued | 3/30/2025 | DEROLD HAUFF |
| Permit Finaled | 3/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/6/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2022 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/10/2023 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/12/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Partial Approval | JOSE AVILA |
| Deputy Wood Construction | 8/28/2023 | Partial Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/22/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/22/2023 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 10/6/2023 | Approved | JOSE AVILA |
| Green Building Rough | 10/6/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 10/6/2023 | Approved | JOSE AVILA |
| Insulation | 10/19/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 10/19/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/5/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/5/2024 | Approved | BRENDAN MORELLI |
| Final | 5/24/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 5/24/2024 | Corrections Issued | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/24/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 5/24/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 5/31/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 5/31/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 5/31/2024 | Approved | ARTHUR NEGRETE |
| Final | 8/14/2024 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 8/14/2024 | Approved | ARTHUR NEGRETE |