632 W CENTURY BLVD 90044
Certificate Information: 632 W CENTURY BLVD 90044
- Application / Permit
- 22014-10000-01294
- Plan Check / Job No.
- B22LA04917
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED 1-STORY GARAGE WITH ADDITION TO ADU PER WFPP per Ordinance.
- Permit Issued
- Issued on 7/1/2022
- Issuing Office
- Metro
- Current Status
- Issued on 7/1/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | AUNG SOE |
| Corrections Issued | 4/6/2022 | AUNG SOE |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| No Progress | 6/27/2022 | JAD BASMA |
| Plan Check Approved | 7/1/2022 | MINA HABILI |
| Issued | 7/1/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 6/17/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 6/21/2022 | AMAAN MALIK |
| Hold | Cleared | 8/23/2022 | PRISCILLA RUIZ |
Contact Information
| Contractor | Precision Construction Experts Inc; Lic. No.: 1026997-B | 16656 CALLE ARBOLADA PACIFIC PALISADES, CA 90272 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/30/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/19/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 9/19/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 9/19/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 9/21/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 9/21/2022 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 9/23/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 9/26/2022 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 9/27/2022 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 9/27/2022 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 9/30/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/22/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 5/22/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Rough | 5/22/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 5/22/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Wood Frame | 5/22/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 6/13/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/13/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Rough | 6/13/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 6/13/2023 | Corrections Issued | JAMES CHAVEZ |
| Wood Frame | 6/13/2023 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 6/22/2023 | No Access for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/22/2023 | No Access for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | No Access for Inspection | JAMES CHAVEZ |
| Green Building Rough | 6/22/2023 | No Access for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 6/22/2023 | No Access for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 6/29/2023 | No Access for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/29/2023 | No Access for Inspection | JAMES CHAVEZ |
| Green Building Rough | 6/29/2023 | No Access for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 6/29/2023 | No Access for Inspection | JAMES CHAVEZ |
| Special/Order Compliance | 6/29/2023 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/5/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 7/5/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 7/14/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Rough | 7/14/2023 | No Access for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 7/14/2023 | No Access for Inspection | JAMES CHAVEZ |
| Wood Frame | 7/14/2023 | No Access for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 7/21/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/25/2023 | No Access for Inspection | JAMES CHAVEZ |
| Interior/Exterior Lathing | 7/25/2023 | No Access for Inspection | JAMES CHAVEZ |
| Interior/Exterior Lathing | 8/3/2023 | Partial Approval | EUGENE CASSIDY |
| Insulation | 8/23/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 8/23/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Wood Frame | 8/23/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Drywall Nailing | 9/1/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/1/2023 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Final | 4/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Final | 4/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Sewer | 4/25/2024 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 4/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 10/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 10/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 10/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Gas Test | 10/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 10/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 10/18/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 10/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 10/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 10/18/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 10/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 10/18/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 4/2/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 4/2/2025 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 4/2/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 4/2/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 4/2/2025 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 4/2/2025 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 3/13/2026 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 3/13/2026 | Corrections Issued | BEN MOLSTAD |
| Final | 3/13/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 3/13/2026 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 3/13/2026 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 3/13/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 3/13/2026 | Approved | BEN MOLSTAD |