8028 S DENROCK AVE 90045
Certificate Information: 8028 S DENROCK AVE 90045
- Application / Permit
- 22014-10000-01288
- Plan Check / Job No.
- B22LA04904
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL, REMOVE PORTION OF EXISTING ONE STORY SFD STRUCTURE AND ONLY TO MAINTAIN PORTION OF EXISTING WALL AND FOOTINGS ON NORTH SIDE. ADD TWO-STORY AND GROUND FLOOR ADDITION. ***SHALL BE SPRINKLERED PER NFPA 13 D***
- Permit Issued
- Issued on 6/7/2022
- Issuing Office
- Current Status
- CofO Issued on 5/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | MICHAEL LOPEZ |
| Corrections Issued | 4/12/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 4/13/2022 | SAI KHUM |
| Applicant returned to address corrections | 5/20/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 6/3/2022 | MICHAEL LOPEZ |
| Issued | 6/7/2022 | APPLICANT |
| CofO in Progress | 5/15/2023 | BOBBY KEY |
| Permit Finaled | 5/16/2023 | DANIEL ORRANTE |
| CofO Issued | 5/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/21/2022 | FREDDY GARCIA |
| Low Impact Development | Cleared | 4/26/2022 | MICHAEL SCADUTO |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 4/29/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 4/29/2022 | CATHERINE ADROVER |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/16/2022 | Partial Approval | BOBBY KEY |
| Sewer | 8/16/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/29/2022 | Partial Approval | BOBBY KEY |
| METHANE-Barrier | 8/29/2022 | Approved | BOBBY KEY |
| METHANE-Subgrade | 8/29/2022 | Approved | BOBBY KEY |
| Deputy Reinf. Concrete | 8/31/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 8/31/2022 | Approved | BOBBY KEY |
| Reinforced Concrete Frame | 8/31/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Partial Approval | BOBBY KEY |
| Deputy Wood Construction | 10/14/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 11/14/2022 | Approved | HERBERT GIRON |
| HVAC-Rough | 11/14/2022 | Conditional Approval | HERBERT GIRON |
| Gas Test | 11/15/2022 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 11/15/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 11/15/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 11/21/2022 | Approved | BOBBY KEY |
| Final | 11/21/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 11/21/2022 | Approved | BOBBY KEY |
| Insulation | 11/21/2022 | Corrections Issued | BOBBY KEY |
| Shower Pan | 11/21/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 11/29/2022 | Approved | HERBERT GIRON |
| Insulation | 11/29/2022 | Approved | HERBERT GIRON |
| Underground Mechanical | 11/29/2022 | Partial Approval | HERBERT GIRON |
| Drywall Nailing | 12/7/2022 | Partial Approval | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 12/7/2022 | Partial Approval | CLAYTON GRAHAM |
| Drywall Nailing | 12/23/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 12/23/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 2/27/2023 | Approved | HERBERT GIRON |
| Sewer | 3/9/2023 | Approved | BOBBY KEY |
| Underground Mechanical | 3/9/2023 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 4/5/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 5/2/2023 | Conditional Approval | BOBBY KEY |
| Final | 5/2/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 5/2/2023 | Approved | BOBBY KEY |
| HVAC-Final | 5/2/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Final | 5/2/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 5/2/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/15/2023 | Approved | BOBBY KEY |
| Final | 5/15/2023 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 5/15/2023 | Approved | BOBBY KEY |
| Service/Power Release | 5/15/2023 | Approved | BOBBY KEY |