9422 W NATIONAL BLVD 90034
Certificate Information: 9422 W NATIONAL BLVD 90034
- Application / Permit
- 22014-10000-01247
- Plan Check / Job No.
- B22LA04767
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION AND 509 sf GROUND FLOOR ADDITION FOR ADU PER LAMC 12.22 A.33 WITH NEW ROOF DECK ON TOP
- Permit Issued
- Issued on 6/7/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 4/23/2022 | MAHNAZ NOURHASHEMI |
| Plans on Hold | 4/28/2022 | TEODORO DIAZ RODRIGUEZ |
| Hold Released | 6/7/2022 | TEODORO DIAZ RODRIGUEZ |
| Quality Review Completed | 6/7/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 6/13/2022 | APPLICANT |
| Applicant returned to address corrections | 8/3/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 4/7/2023 | SUNMIN LEE |
| Issued | 6/7/2023 | APPLICANT |
| Permit Finaled | 5/11/2026 | RICHARD STEINBACH |
| CofO Issued | 5/11/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/11/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hold | Cleared | 6/3/2022 | JASON SHEETS |
| Address approval | Cleared | 6/13/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2022 | DINAH GARIN |
| Sewer availability | Cleared | 11/10/2022 | DINAH GARIN |
| Low Impact Development | Cleared | 12/27/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/11/2023 | JENSON LEE |
| Tenant Habitability Plan | Cleared | 1/26/2023 | ISMAEL HERNANDEZ |
| Grading Pre-Inspection | Cleared | 2/3/2023 | KIRK LINKLATER |
| Highway dedication | Cleared | 2/28/2023 | AHMED AMARRAGY |
| Specific Plan | Cleared | 3/23/2023 | KYLE WINSTON |
| ZI | Cleared | 3/23/2023 | KYLE WINSTON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 6/13/2023 | Partial Approval | CLAYTON GRAHAM |
| Underground Mechanical | 6/20/2023 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 6/26/2023 | Corrections Issued | CLAYTON GRAHAM |
| Underground Mechanical | 6/26/2023 | Corrections Issued | CLAYTON GRAHAM |
| Underground Mechanical | 6/30/2023 | Partial Approval | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 7/31/2023 | No Access for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 7/31/2023 | No Access for Inspection | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 8/7/2023 | Corrections Issued | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 8/16/2023 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 9/6/2023 | Corrections Issued | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 9/14/2023 | Corrections Issued | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 10/2/2023 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/11/2023 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/20/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 12/20/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 12/20/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 12/20/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Rough | 12/20/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/20/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/22/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 1/18/2024 | Approved | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 1/18/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/22/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/22/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/23/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/25/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 1/25/2024 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 1/25/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/25/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 2/2/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Drywall Nailing | 2/9/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Drywall Nailing | 2/26/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 3/7/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 3/12/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/14/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 3/14/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 7/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 7/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 7/26/2024 | Approved | ASHLEY THOMPSON |
| Green Building Final | 7/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 7/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| MERV13>=Final | 7/26/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 7/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 7/26/2024 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 7/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 11/8/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Final | 11/8/2024 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 11/8/2024 | Approved | ASHLEY THOMPSON |
| Final | 4/30/2026 | Partial Approval | ASHLEY THOMPSON |
| Final | 5/5/2026 | Conditional Approval | ASHLEY THOMPSON |