4045 W EDENHURST AVE 90039

Certificate Information: 4045 W EDENHURST AVE 90039

Application / Permit
22014-10000-01241
Plan Check / Job No.
B22LA04746
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW BATHROOM ADDITION TO (E) 1-STORY SFD.
Permit Issued
Issued on 4/16/2025
Issuing Office
Metro
Current Status
Issued on 4/16/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/30/2022 SAMUEL GONZALEZ
Corrections Issued 3/31/2022 SAMUEL GONZALEZ
Building Plans Picked Up 4/8/2022 APPLICANT
Applicant returned to address corrections 6/22/2022 ADRIANA LOPEZ
Applicant returned to address corrections 2/8/2023 CRISTINA SALAZAR
Plan Check Approved 2/22/2023 CRISTINA SALAZAR
Plan Check Approved 2/22/2023 EDWIN MARTINEZ
Issued 4/16/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/20/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/22/2022 JEANIE LAM

Contact Information

Contractor A C Power Electric; Lic. No.: 1020813-B 4114 1/2 EAST 56TH STREET      MAYWOOD, CA 90270
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/30/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 4/30/2025 Corrections Issued NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 5/14/2025 Partial Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval REGINA MENDEZ
ELECTRICAL-Rough 6/13/2025 Approved NICHOLAS LOPEZ
Footing/Foundation/Slab 6/13/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 6/13/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 6/13/2025 Approved NICHOLAS LOPEZ
Shower Pan 6/13/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 6/23/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 6/27/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 6/27/2025 Approved ALIZAH MAYAGOITIA
Insulation 6/27/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/27/2025 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 7/8/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 7/8/2025 Partial Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 7/10/2025 Approved REGINA MENDEZ
Final 9/3/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 9/3/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 9/3/2025 Approved NICHOLAS LOPEZ
Final 9/16/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 9/16/2025 Not Ready for Inspection NICHOLAS LOPEZ