827 1/2 E 33RD ST 90011

Certificate Information: 827 1/2 E 33RD ST 90011

Application / Permit
22014-10000-01229
Plan Check / Job No.
B22LA04666
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY ADDITION (171 SQ.FT.) AND CONVERT ENTIRE REAR SFD TO AN ADU PER LAMC 12.22 A.33 (c)-(d). ALL WORK DONE PER WFPP
Permit Issued
Issued on 3/30/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/30/2022 SAMUEL GONZALEZ
Corrections Issued 3/31/2022 SAMUEL GONZALEZ
Building Plans Picked Up 4/8/2022 APPLICANT
Plan Check Approved 6/15/2022 KHUONG TRUONG
Issued 3/30/2023 APPLICANT
CofO in Progress 2/28/2024 SCOTT FINNILA
Permit Finaled 3/5/2024 DEROLD HAUFF
CofO Issued 3/5/2024 DEROLD HAUFF
Permit Finaled 3/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 5/25/2022 MICHAEL SOTO
Address approval Cleared 6/2/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 6/2/2022 TREVOR QUAN
Sewer availability Cleared 6/2/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 6/3/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/4/2023 Partial Inspection BRENDAN MORELLI
Deputy Drilled-In Anchors 4/14/2023 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 4/18/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 5/1/2023 Partial Approval BRENDAN MORELLI
Insulation 5/1/2023 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval BRENDAN MORELLI
Insulation 5/8/2023 Partial Approval BRENDAN MORELLI
ELECTRICAL-Final 6/30/2023 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Corrections Issued JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/10/2023 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/30/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/30/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/7/2023 Approved ALEJANDRO DE ARTOLA
Green Building Rough 9/7/2023 Approved ALEJANDRO DE ARTOLA
Insulation 9/7/2023 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 9/14/2023 Approved JOSEPH MCGARRY
ELECTRICAL-Final 9/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 9/25/2023 Approved ALEJANDRO DE ARTOLA
Final 10/3/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/3/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/15/2023 Approved ALEJANDRO DE ARTOLA
Final 11/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/15/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/15/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/15/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Final 2/28/2024 OK to Issue CofO SCOTT FINNILA