1572-1578 N MURRAY DR 90026
Certificate Information: 1572-1578 N MURRAY DR 90026
- Application / Permit
- 22014-10000-01212
- Plan Check / Job No.
- B22LA04627
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- GROUND ADDITION 184 SF TO EXISTING 1-STORY DUPLEX TO ENLARGE 2 BEDROOMS, ADD A POWDER ROOM AND ENLARGE 1 BATHROOM. 1 OF 2
- Permit Issued
- Issued on 1/6/2023
- Issuing Office
- Metro
- Current Status
- Issued on 1/6/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | CHUNG-WEN CHUANG |
| Corrections Issued | 4/25/2022 | CHUNG-WEN CHUANG |
| Quality Review Completed | 5/3/2022 | SAI KHUM |
| Building Plans Picked Up | 7/21/2022 | APPLICANT |
| Applicant returned to address corrections | 9/7/2022 | CHUNG-WEN CHUANG |
| Plan Check Approved | 12/30/2022 | CHUNG-WEN CHUANG |
| Issued | 1/6/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/11/2022 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/12/2022 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 10/27/2022 | RICARDO BOHORQUEZ |
| GPI Written Notices | Cleared | 11/16/2022 | SAI KHUM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/27/2023 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 2/6/2023 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 2/8/2023 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/9/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 3/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Wood Construction | 4/5/2023 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 4/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 4/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/28/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/18/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 5/18/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 5/18/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 5/18/2023 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/25/2023 | Corrections Issued | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 5/25/2023 | Conditional Approval | THOMAS LOGRASSO |
| Insulation | 6/2/2023 | Partial Inspection | JOSEPH MCGARRY |
| Shower Pan | 6/2/2023 | Approved | JOSEPH MCGARRY |
| Wood Frame | 6/2/2023 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/5/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 6/5/2023 | Approved | STUART CHAPMAN |
| Insulation | 6/5/2023 | Corrections Issued | STUART CHAPMAN |
| Drywall Nailing | 6/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |