850 N FISKE ST 90272
Certificate Information: 850 N FISKE ST 90272
- Application / Permit
- 22014-10000-01193
- Plan Check / Job No.
- B22LA04592
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT (E) GARAGE TO 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 6/30/2022
- Issuing Office
- Current Status
- CofO Issued on 5/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2022 | DANIEL YIP |
| Corrections Issued | 3/17/2022 | DANIEL YIP |
| Applicant returned to address corrections | 4/14/2022 | DANIEL YIP |
| Applicant returned to address corrections | 4/21/2022 | DANIEL YIP |
| Applicant returned to address corrections | 4/26/2022 | DANIEL YIP |
| Plan Check Approved | 5/6/2022 | DANIEL YIP |
| Issued | 6/30/2022 | APPLICANT |
| CofO in Progress | 5/16/2023 | KEVIN SARGSYAN |
| CofO in Progress | 5/16/2023 | KEVIN SARGSYAN |
| Permit Finaled | 5/16/2023 | DANIEL ORRANTE |
| CofO Issued | 5/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/20/2022 | ROBERT HUGHES |
| Address approval | Cleared | 4/21/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2022 | JENSON LEE |
| Sewer availability | Cleared | 4/21/2022 | DINAH GARIN |
| Construction near power lines | Cleared | 5/4/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/13/2022 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 8/5/2022 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Inspection | 8/5/2022 | Partial Inspection | KEVIN SARGSYAN |
| Pre-Inspection | 8/16/2022 | Partial Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/6/2022 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/18/2022 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/18/2022 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/29/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/29/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 12/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/9/2022 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/13/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 12/13/2022 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 12/13/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 12/13/2022 | Approved | KEVIN SARGSYAN |
| Insulation | 12/15/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 12/16/2022 | Corrections Issued | KEVIN SARGSYAN |
| Insulation | 12/16/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/16/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 12/29/2022 | Approved | KEVIN SARGSYAN |
| Gas Test | 2/14/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Gas Test | 2/28/2023 | Corrections Issued | BRENDAN LOONEY |
| Gas Test | 3/10/2023 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/18/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 4/18/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/18/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 4/26/2023 | Partial Approval | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 5/16/2023 | OK to Issue CofO | KEVIN SARGSYAN |