850 N FISKE ST 90272

Certificate Information: 850 N FISKE ST 90272

Application / Permit
22014-10000-01193
Plan Check / Job No.
B22LA04592
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) GARAGE TO 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 6/30/2022
Issuing Office
Current Status
CofO Issued on 5/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/16/2022 DANIEL YIP
Corrections Issued 3/17/2022 DANIEL YIP
Applicant returned to address corrections 4/14/2022 DANIEL YIP
Applicant returned to address corrections 4/21/2022 DANIEL YIP
Applicant returned to address corrections 4/26/2022 DANIEL YIP
Plan Check Approved 5/6/2022 DANIEL YIP
Issued 6/30/2022 APPLICANT
CofO in Progress 5/16/2023 KEVIN SARGSYAN
CofO in Progress 5/16/2023 KEVIN SARGSYAN
Permit Finaled 5/16/2023 DANIEL ORRANTE
CofO Issued 5/16/2023 DANIEL ORRANTE
Permit Finaled 5/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/20/2022 ROBERT HUGHES
Address approval Cleared 4/21/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/21/2022 JENSON LEE
Sewer availability Cleared 4/21/2022 DINAH GARIN
Construction near power lines Cleared 5/4/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/13/2022 Partial Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 8/5/2022 Corrections Issued KEVIN SARGSYAN
Pre-Inspection 8/5/2022 Partial Inspection KEVIN SARGSYAN
Pre-Inspection 8/16/2022 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 10/6/2022 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 11/18/2022 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 11/18/2022 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 11/29/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 11/29/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 12/7/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 12/9/2022 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 12/13/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 12/13/2022 Approved KEVIN SARGSYAN
Green Building Rough 12/13/2022 Approved KEVIN SARGSYAN
HVAC-Rough 12/13/2022 Approved KEVIN SARGSYAN
Insulation 12/15/2022 Not Ready for Inspection KEVIN SARGSYAN
Final 12/16/2022 Corrections Issued KEVIN SARGSYAN
Insulation 12/16/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/16/2022 Approved KEVIN SARGSYAN
Drywall Nailing 12/29/2022 Approved KEVIN SARGSYAN
Gas Test 2/14/2023 Corrections Issued OGANES TARAKHCHYAN
Gas Test 2/28/2023 Corrections Issued BRENDAN LOONEY
Gas Test 3/10/2023 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/18/2023 Approved OGANES TARAKHCHYAN
Green Building Final 4/18/2023 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 4/18/2023 Approved OGANES TARAKHCHYAN
Final 4/26/2023 Partial Approval OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/26/2023 SGSOV Approved OGANES TARAKHCHYAN
Final 5/16/2023 OK to Issue CofO KEVIN SARGSYAN