3250 S STONER AVE 90066
Certificate Information: 3250 S STONER AVE 90066
- Application / Permit
- 22014-10000-01170
- Plan Check / Job No.
- B22LA04492
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- STRUCTURAL REMODEL AND 1ST FLOOR AND 2ND FLOOR ADDITION TO AN EXISTING 1-STORY SFD.
- Permit Issued
- Issued on 11/16/2022
- Issuing Office
- Current Status
- CofO Issued on 7/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 3/31/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 4/12/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 4/15/2022 | APPLICANT |
| Applicant returned to address corrections | 6/24/2022 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 9/26/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 11/1/2022 | MAHNAZ NOURHASHEMI |
| Issued | 11/16/2022 | APPLICANT |
| CofO in Progress | 7/18/2025 | WILBER ROSALES |
| Permit Finaled | 7/19/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/19/2025 | RICHARD STEINBACH |
| CofO Issued | 7/19/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 6/24/2022 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 6/24/2022 | MAHNAZ NOURHASHEMI |
| Low Impact Development | Cleared | 10/13/2022 | CHRIS VONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 10/17/2022 | CINDY QI |
| Sewer availability | Cleared | 10/17/2022 | CINDY QI |
| Specific Plan | Cleared | 10/25/2022 | FREDDY GARCIA |
Contact Information
| Contractor | Steiner Joel; Lic. No.: 846118-B | 10763 GALVIN STREET CULVER CITY, CA 90230 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/30/2022 | Partial Approval | ASHLEY THOMPSON |
| Deputy Drilled-In Anchors | 1/25/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 2/3/2023 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 3/2/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 6/12/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/12/2023 | Approved | JOHNNY MIRANDA |
| Sewer | 6/12/2023 | Approved | JOHNNY MIRANDA |
| Deputy Wood Construction | 6/13/2023 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Conditional Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 7/13/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/13/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 7/13/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/13/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 7/19/2023 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 7/25/2023 | Approved | EVAN COOPER |
| Shower Pan | 7/25/2023 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 7/25/2023 | Approved | EVAN COOPER |
| Insulation | 8/3/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 8/11/2023 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/21/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/13/2023 | Approved | BEN MOLSTAD |
| Underground Mechanical | 11/2/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 1/16/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 1/16/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 1/16/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 1/16/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 7/17/2025 | Approved | WILBER ROSALES |
| Final | 7/17/2025 | OK to Issue CofO | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 7/17/2025 | Approved | WILBER ROSALES |