3250 S STONER AVE 90066

Certificate Information: 3250 S STONER AVE 90066

Application / Permit
22014-10000-01170
Plan Check / Job No.
B22LA04492
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
STRUCTURAL REMODEL AND 1ST FLOOR AND 2ND FLOOR ADDITION TO AN EXISTING 1-STORY SFD.
Permit Issued
Issued on 11/16/2022
Issuing Office
Current Status
CofO Issued on 7/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 MAHNAZ NOURHASHEMI
Corrections Issued 3/31/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 4/12/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 4/15/2022 APPLICANT
Applicant returned to address corrections 6/24/2022 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 9/26/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 11/1/2022 MAHNAZ NOURHASHEMI
Issued 11/16/2022 APPLICANT
CofO in Progress 7/18/2025 WILBER ROSALES
Permit Finaled 7/19/2025 RICHARD STEINBACH
Permit Finaled 7/19/2025 RICHARD STEINBACH
CofO Issued 7/19/2025 RICHARD STEINBACH

Permit Application Clearance Information

GPI Written Notices Cleared 6/24/2022 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 6/24/2022 MAHNAZ NOURHASHEMI
Low Impact Development Cleared 10/13/2022 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 10/17/2022 CINDY QI
Roof/Waste drainage to street Cleared 10/17/2022 CINDY QI
Sewer availability Cleared 10/17/2022 CINDY QI
Specific Plan Cleared 10/25/2022 FREDDY GARCIA

Contact Information

Contractor Steiner Joel; Lic. No.: 846118-B 10763 GALVIN STREET      CULVER CITY, CA 90230
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/30/2022 Partial Approval ASHLEY THOMPSON
Deputy Drilled-In Anchors 1/25/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 2/3/2023 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Partial Approval JOHNNY MIRANDA
Green Building Rough 3/2/2023 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 6/12/2023 Approved JOHNNY MIRANDA
PLUMBING-Rough 6/12/2023 Approved JOHNNY MIRANDA
Sewer 6/12/2023 Approved JOHNNY MIRANDA
Deputy Wood Construction 6/13/2023 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Conditional Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 7/13/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 7/13/2023 Approved JESUS RODRIGUEZ
Green Building Rough 7/13/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/13/2023 Approved JESUS RODRIGUEZ
Shower Pan 7/19/2023 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 7/25/2023 Approved EVAN COOPER
Shower Pan 7/25/2023 Approved EVAN COOPER
Verify Sprinkler Sign Off 7/25/2023 Approved EVAN COOPER
Insulation 8/3/2023 Approved JESUS PINEDA
Drywall Nailing 8/11/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 8/21/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 9/13/2023 Approved BEN MOLSTAD
Underground Mechanical 11/2/2023 Approved JESUS PINEDA
ELECTRICAL-Final 1/16/2024 Corrections Issued JESUS PINEDA
Green Building Final 1/16/2024 Approved JESUS PINEDA
HVAC-Final 1/16/2024 Approved JESUS PINEDA
PLUMBING-Final 1/16/2024 Approved JESUS PINEDA
ELECTRICAL-Final 7/17/2025 Approved WILBER ROSALES
Final 7/17/2025 OK to Issue CofO WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 7/17/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 7/17/2025 Approved WILBER ROSALES