1849 W 66TH ST 90047

Certificate Information: 1849 W 66TH ST 90047

Application / Permit
22014-10000-01168
Plan Check / Job No.
B22LA04485
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
380 SQ.FT. NEW ADDITION TO EXISTING SFD.
Permit Issued
Issued on 6/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 KHUONG TRUONG
Corrections Issued 3/17/2022 KHUONG TRUONG
Building Plans Picked Up 3/18/2022 APPLICANT
Applicant returned to address corrections 5/26/2022 ADAM HEGAZI
Plan Check Approved 5/31/2022 FERNANDO FLORES
Issued 6/7/2022 APPLICANT
CofO in Progress 7/5/2023 ENRIQUE MIRELES
CofO in Progress 7/5/2023 ENRIQUE MIRELES
CofO Issued 7/14/2023 DEROLD HAUFF
Permit Finaled 7/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/8/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 5/26/2022 AMAAN MALIK
Sewer availability Cleared 5/26/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Vo,, Tung Thanh; Lic. No.: C69546 11122 BIXLER CIRCLE      GARDEN GROVE, CA 92840

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/9/2022 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/14/2022 Corrections Issued ENRIQUE MIRELES
Pre-Inspection 6/14/2022 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/23/2022 Approved HORACE FULTZ
Pre-Inspection 6/23/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 6/28/2022 No Access for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 6/28/2022 Approved ENRIQUE MIRELES
Pre-Inspection 6/28/2022 Approved ENRIQUE MIRELES
Insulation 7/5/2022 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 7/5/2022 Corrections Issued ENRIQUE MIRELES
Insulation 7/8/2022 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 7/13/2022 Corrections Issued ENRIQUE MIRELES
Green Building Rough 7/13/2022 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 7/22/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 8/3/2022 Corrections Issued ENRIQUE MIRELES
Insulation 8/4/2022 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 8/8/2022 Partial Approval ENRIQUE MIRELES
Insulation 8/11/2022 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 8/24/2022 Approved ENRIQUE MIRELES
Drywall Nailing 8/24/2022 Approved ENRIQUE MIRELES
Green Building Rough 8/24/2022 Approved ENRIQUE MIRELES
Pre-Inspection 9/30/2022 No Access for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 12/12/2022 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 12/20/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/27/2022 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 1/6/2023 Corrections Issued ENRIQUE MIRELES
Service/Power Release 1/26/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 4/7/2023 Approved ENRIQUE MIRELES
Final 4/7/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/7/2023 Approved ENRIQUE MIRELES
HVAC-Final 4/7/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 4/7/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/7/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 4/7/2023 Approved ENRIQUE MIRELES
Final 4/25/2023 Corrections Issued ENRIQUE MIRELES
Final 5/22/2023 Corrections Issued ENRIQUE MIRELES
Final 5/31/2023 Corrections Issued ENRIQUE MIRELES
Final 6/21/2023 Corrections Issued ENRIQUE MIRELES
Final 6/29/2023 OK to Issue CofO ENRIQUE MIRELES