3222 N LOWELL AVE 90032
Certificate Information: 3222 N LOWELL AVE 90032
- Application / Permit
- 22014-10000-01162
- Plan Check / Job No.
- B22LA04452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1 STORY ADDITION TO REAR OF (E) ONE STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 4/11/2022
- Issuing Office
- Current Status
- CofO Issued on 2/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | AUNG SOE |
| Corrections Issued | 3/21/2022 | AUNG SOE |
| Plan Check Approved | 4/5/2022 | FERNANDO FLORES |
| Issued | 4/11/2022 | APPLICANT |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| CofO in Progress | 1/31/2023 | AMY COLIN |
| Permit Finaled | 2/4/2023 | DEROLD HAUFF |
| Permit Finaled | 2/4/2023 | DEROLD HAUFF |
| CofO Issued | 2/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/25/2022 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 3/29/2022 | CINDY QI |
| Sewer availability | Cleared | 3/29/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2022 | CINDY QI |
| GPI Written Notices | Cleared | 4/4/2022 | AUNG SOE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/4/2022 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 5/12/2022 | Partial Approval | RUBEN SALAS |
| Green Building Rough | 5/12/2022 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 5/12/2022 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 6/3/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/3/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 6/3/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 6/3/2022 | Approved | OSVALDO PARAMO |
| Insulation | 6/9/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 6/9/2022 | Partial Approval | RUBEN SALAS |
| Shower Pan | 6/9/2022 | Approved | RUBEN SALAS |
| Drywall Nailing | 6/13/2022 | Approved | RUBEN SALAS |
| Final | 11/28/2022 | No Access for Inspection | AMY COLIN |
| Green Building Final | 11/28/2022 | No Access for Inspection | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Not Ready | AMY COLIN |
| Smoke Detectors | 11/28/2022 | No Access for Inspection | AMY COLIN |
| Final | 12/2/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Final | 12/2/2022 | Corrections Issued | AMY COLIN |
| Pre-Inspection | 12/2/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 12/2/2022 | Approved | AMY COLIN |
| Final | 1/31/2023 | OK to Issue CofO | AMY COLIN |
| Green Building Final | 1/31/2023 | Approved | AMY COLIN |