10219 N KESTER AVE 91345

Certificate Information: 10219 N KESTER AVE 91345

Application / Permit
22014-10000-01161
Plan Check / Job No.
B22LA04446
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADITION WITH NEW MASTER BEDROOM, MASTER BATHROOM, MASTER CLOSET, AND DINNING AREA ADJACENT TO EXISTING LIVING AREA TOWARDS REAR OF EXISTING SINGLE FAMILY RESIDENCE
Permit Issued
Issued on 5/24/2022
Issuing Office
Current Status
CofO Issued on 8/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 ADAM HEGAZI
Corrections Issued 3/21/2022 ADAM HEGAZI
Applicant returned to address corrections 4/23/2022 SINA KHOSRAVI
Plan Check Approved 4/26/2022 SINA KHOSRAVI
Building Plans Picked Up 5/5/2022 APPLICANT
Issued 5/24/2022 APPLICANT
CofO in Progress 8/4/2022 JENNIFER RABUCHIN
CofO in Progress 8/5/2022 JENNIFER RABUCHIN
Permit Finaled 8/5/2022 RONALD MYRICK
CofO Issued 8/5/2022 RONALD MYRICK
Permit Finaled 8/5/2022 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/7/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/8/2022 LEE GUILBEAUX
Sewer availability Cleared 4/8/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/8/2022 LEE GUILBEAUX

Contact Information

Contractor R & M Construction; Lic. No.: 847093-B 11329 COLLETT AVE      GRANADA HILLS, CA 91344
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/26/2022 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 5/27/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/9/2022 Partial Approval JENNIFER RABUCHIN
Insulation 6/9/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/9/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 6/21/2022 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/21/2022 Approved JENNIFER RABUCHIN
Deputy Wood Construction 6/22/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 6/23/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/29/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Green Building Rough 6/29/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 6/29/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 6/29/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Shower Pan 6/29/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 7/7/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/7/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/2/2022 Approved JENNIFER RABUCHIN
Final 8/2/2022 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 8/2/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 8/2/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/5/2022 Approved JENNIFER RABUCHIN
Final 8/5/2022 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 8/5/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/5/2022 Approved JENNIFER RABUCHIN