6525 W 85TH ST 90045

Certificate Information: 6525 W 85TH ST 90045

Application / Permit
22014-10000-01157
Plan Check / Job No.
B22LA04442
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF EXISTING 18X20 FT. DETACHED GARAGE TO ACCESSORY DWELLING UNIT. ( per Ordinance,LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 6/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 3/18/2022 TSE MING HUANG
Corrections Issued 3/19/2022 TSE MING HUANG
Applicant returned to address corrections 4/21/2022 LUKE GONZALES
Building Plans Picked Up 4/22/2022 APPLICANT
Applicant returned to address corrections 6/16/2022 AUNG SOE
Plan Check Approved 6/29/2022 SHANGQIN XIE
Issued 6/29/2022 APPLICANT
CofO in Progress 3/3/2023 HERBERT GIRON
Permit Finaled 3/6/2023 DANIEL ORRANTE
CofO Issued 3/6/2023 DANIEL ORRANTE
Permit Finaled 3/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/27/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 4/28/2022 JENSON LEE
Roof/Waste drainage to street Cleared 4/28/2022 JENSON LEE
Sewer availability Cleared 5/3/2022 JENSON LEE
Construction near power lines Cleared 6/3/2022 RIDWAN HARDY
Construction within easement Cleared 6/3/2022 RIDWAN HARDY
Specific Plan Cleared 6/20/2022 EDUARDO HERMOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Graciano,, Santiago; Lic. No.: S6167 448 E FOOTHILL BLVD STE 206      SAN DIEGO, CA 91773

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/25/2022 Partial Approval HERBERT GIRON
PLUMBING-Rough 8/25/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 9/23/2022 Corrections Issued HERBERT GIRON
Green Building Rough 9/23/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 9/23/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 9/23/2022 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 9/28/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 9/28/2022 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 9/28/2022 Corrections Issued HERBERT GIRON
Green Building Rough 9/28/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 9/28/2022 Approved HERBERT GIRON
PLUMBING-Rough 9/28/2022 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/4/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 10/4/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 10/4/2022 Approved HERBERT GIRON
Green Building Rough 10/4/2022 Not Ready for Inspection HERBERT GIRON
Pre-Inspection 10/4/2022 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Approved HERBERT GIRON
Deputy Wood Construction 10/12/2022 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 10/17/2022 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 10/21/2022 Corrections Issued HERBERT GIRON
Green Building Rough 10/21/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 10/21/2022 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/25/2022 Partial Approval HERBERT GIRON
Insulation 10/28/2022 Approved DAVID FEILER
Drywall Nailing 11/2/2022 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 11/7/2022 Approved HERBERT GIRON
Shower Pan 11/7/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 11/10/2022 Approved HERBERT GIRON
Service/Power Release 12/22/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 2/14/2023 Corrections Issued HERBERT GIRON
Gas Test 2/14/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 2/17/2023 Corrections Issued HERBERT GIRON
Gas Test 2/17/2023 Approved HERBERT GIRON
HVAC-Final 2/17/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 2/17/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 2/23/2023 Not Ready for Inspection BOBBY KEY
Final 2/23/2023 Not Ready for Inspection BOBBY KEY
Green Building Final 2/23/2023 Approved BOBBY KEY
HVAC-Final 2/23/2023 Approved BOBBY KEY
PLUMBING-Final 2/23/2023 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Not Ready BOBBY KEY
Smoke Detectors 2/23/2023 Approved BOBBY KEY
ELECTRICAL-Final 2/28/2023 Approved HERBERT GIRON
Final 2/28/2023 Conditional Approval HERBERT GIRON
PLUMBING-Final 2/28/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved HERBERT GIRON
Service/Power Release 2/28/2023 Not Ready for Inspection HERBERT GIRON
Final 3/3/2023 OK to Issue CofO HERBERT GIRON