6525 W 85TH ST 90045
Certificate Information: 6525 W 85TH ST 90045
- Application / Permit
- 22014-10000-01157
- Plan Check / Job No.
- B22LA04442
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERSION OF EXISTING 18X20 FT. DETACHED GARAGE TO ACCESSORY DWELLING UNIT. ( per Ordinance,LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 6/29/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2022 | TSE MING HUANG |
| Corrections Issued | 3/19/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 4/21/2022 | LUKE GONZALES |
| Building Plans Picked Up | 4/22/2022 | APPLICANT |
| Applicant returned to address corrections | 6/16/2022 | AUNG SOE |
| Plan Check Approved | 6/29/2022 | SHANGQIN XIE |
| Issued | 6/29/2022 | APPLICANT |
| CofO in Progress | 3/3/2023 | HERBERT GIRON |
| Permit Finaled | 3/6/2023 | DANIEL ORRANTE |
| CofO Issued | 3/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 4/28/2022 | JENSON LEE |
| Sewer availability | Cleared | 5/3/2022 | JENSON LEE |
| Construction near power lines | Cleared | 6/3/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/3/2022 | RIDWAN HARDY |
| Specific Plan | Cleared | 6/20/2022 | EDUARDO HERMOSO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Graciano,, Santiago; Lic. No.: S6167 | 448 E FOOTHILL BLVD STE 206 SAN DIEGO, CA 91773 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/25/2022 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 8/25/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 9/23/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 9/23/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 9/23/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 9/23/2022 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/28/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 9/28/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 9/28/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 9/28/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 9/28/2022 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 9/28/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/4/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 10/4/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 10/4/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 10/4/2022 | Not Ready for Inspection | HERBERT GIRON |
| Pre-Inspection | 10/4/2022 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Approved | HERBERT GIRON |
| Deputy Wood Construction | 10/12/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 10/17/2022 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/21/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 10/21/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 10/21/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/25/2022 | Partial Approval | HERBERT GIRON |
| Insulation | 10/28/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 11/2/2022 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | HERBERT GIRON |
| Shower Pan | 11/7/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 11/10/2022 | Approved | HERBERT GIRON |
| Service/Power Release | 12/22/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 2/14/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 2/14/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 2/17/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 2/17/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 2/17/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 2/17/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 2/23/2023 | Not Ready for Inspection | BOBBY KEY |
| Final | 2/23/2023 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 2/23/2023 | Approved | BOBBY KEY |
| HVAC-Final | 2/23/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 2/23/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/23/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 2/23/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 2/28/2023 | Approved | HERBERT GIRON |
| Final | 2/28/2023 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Final | 2/28/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Approved | HERBERT GIRON |
| Service/Power Release | 2/28/2023 | Not Ready for Inspection | HERBERT GIRON |
| Final | 3/3/2023 | OK to Issue CofO | HERBERT GIRON |