749 1/2 E 92ND ST 90002
Certificate Information: 749 1/2 E 92ND ST 90002
- Application / Permit
- 22014-10000-01153
- Plan Check / Job No.
- B22LA04422
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2ND FLOOR ADDITION AND CONVERT GARAGE TO ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | KHEDER ALRAZAA |
| Corrections Issued | 3/24/2022 | KHEDER ALRAZAA |
| Quality Review Completed | 4/5/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Plan Check Approved | 8/24/2022 | KHEDER ALRAZAA |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 6/1/2023 | MICHAEL LEWIS |
| Permit Finaled | 6/11/2023 | DEROLD HAUFF |
| CofO Issued | 6/11/2023 | DEROLD HAUFF |
| Permit Finaled | 6/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/10/2022 | CELINA MORENO |
| Address approval | Cleared | 7/12/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 7/25/2022 | STEVE MELGAR |
Contact Information
| Contractor | Acosta Armando; Lic. No.: 1064515-B | 2609 SYCAMORE LN PALMDALE, CA 93551 |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/11/2022 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/14/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 11/3/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/7/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 12/7/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/4/2023 | No Access for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 1/4/2023 | No Access for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/4/2023 | No Access for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 1/4/2023 | No Access for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/6/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 1/6/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 1/6/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/13/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/13/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/13/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/13/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Special/Order Compliance | 1/13/2023 | Partial Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/19/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 1/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/19/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/19/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/19/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/19/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 1/27/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/31/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 1/31/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/6/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/10/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 5/10/2023 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 5/10/2023 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 5/10/2023 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Final | 5/15/2023 | Approved | MICHAEL LEWIS |
| Final | 5/15/2023 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 5/15/2023 | Approved | MICHAEL LEWIS |
| Final | 5/30/2023 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 5/30/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 5/30/2023 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 5/30/2023 | Approved | MICHAEL LEWIS |