1224 N AVENUE 45 90041
Certificate Information: 1224 N AVENUE 45 90041
- Application / Permit
- 22014-10000-01148
- Plan Check / Job No.
- B22LA04414
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION TO EXISTING 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 1-CAR GARAGE
- Permit Issued
- Issued on 4/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2022 | SUNMIN LEE |
| Corrections Issued | 5/18/2022 | PRANITA SHAH |
| Quality Review Completed | 5/24/2022 | KEN GILL |
| Building Plans Picked Up | 6/17/2022 | APPLICANT |
| Applicant returned to address corrections | 2/9/2023 | SUNMIN LEE |
| Plan Check Approved | 2/23/2023 | SUNMIN LEE |
| Issued | 4/5/2023 | APPLICANT |
| CofO in Progress | 1/16/2026 | NICHOLAS LOPEZ |
| Permit Finaled | 1/17/2026 | DEROLD HAUFF |
| CofO Issued | 1/17/2026 | DEROLD HAUFF |
| Permit Finaled | 1/17/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/21/2022 | PRANITA SHAH |
| Grading Pre-Inspection | Cleared | 10/21/2022 | PRANITA SHAH |
| Roof/Waste drainage to street | Cleared | 11/16/2022 | JEANIE LAM |
| Sewer availability | Cleared | 11/16/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2022 | JEANIE LAM |
| Excavation more than 5-ft deep | Cleared | 2/9/2023 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
| Engineer | Cai,, Luo; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/14/2023 | Approved | HAMIK HARTOUNIAN |
| Deputy Grading | 7/12/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 7/12/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 7/19/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/21/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 7/27/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 9/22/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 9/29/2023 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 10/13/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 10/13/2023 | Approved | ROY SPAULDING |
| Deputy Reinf. Concrete | 10/16/2023 | Conditional Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/20/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Shotcrete | 10/23/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/27/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Sewer | 11/2/2023 | Approved | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 11/13/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2024 | Partial Approval | BRENDAN MORELLI |
| Insulation | 2/2/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Rough | 3/8/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/8/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/15/2024 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 3/15/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/27/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/27/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/2/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 4/2/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/1/2024 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/23/2024 | Approved | BRENDAN MORELLI |
| Green Building Rough | 5/23/2024 | Conditional Approval | BRENDAN MORELLI |
| HVAC-Rough | 5/23/2024 | Partial Approval | BRENDAN MORELLI |
| Service/Power Release | 5/23/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Wood Frame | 5/23/2024 | Conditional Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/21/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/21/2024 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 8/21/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/29/2024 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 9/12/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 10/18/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/12/2025 | Approved | THOMAS LOGRASSO |
| Shower Pan | 2/12/2025 | Approved | THOMAS LOGRASSO |
| Special/Order Compliance | 4/22/2025 | Corrections Issued | JACOB SEGURA |
| ELECTRICAL-Final | 7/9/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 7/9/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 7/9/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 8/13/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 8/13/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 8/13/2025 | Approved | NICHOLAS LOPEZ |
| Final | 10/22/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 10/22/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 10/22/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV No Gas | NICHOLAS LOPEZ |
| Smoke Detectors | 10/22/2025 | Approved | NICHOLAS LOPEZ |
| Grading Pre-Inspection | 1/2/2026 | Partial Inspection | NICHOLAS LOPEZ |
| Final | 1/16/2026 | OK to Issue CofO | NICHOLAS LOPEZ |