1958 W 74TH ST 90047

Certificate Information: 1958 W 74TH ST 90047

Application / Permit
22014-10000-01141
Plan Check / Job No.
B22LA04378
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One-story, ground floor addition to the rear of (E) one-story Single Family Dwelling and interior remodel.
Permit Issued
Issued on 5/17/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2022 APPLICANT
Assigned to Plan Check Engineer 3/16/2022 TSE MING HUANG
Corrections Issued 3/16/2022 TSE MING HUANG
Applicant returned to address corrections 4/5/2022 TSE MING HUANG
Building Plans Picked Up 4/18/2022 APPLICANT
Applicant returned to address corrections 5/9/2022 FERNANDO FLORES
Plan Check Approved 5/17/2022 CHRISTOPHER KOMANCHECK
Issued 5/17/2022 APPLICANT
CofO in Progress 3/8/2024 DAVID FEILER
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/12/2022 STEVE MELGAR
Sewer availability Cleared 5/12/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 5/13/2022 STEVE MELGAR

Contact Information

Contractor Taylors Construction; Lic. No.: 267742-B 5301 WEST BLVD      LOS ANGELES, CA 90043
Engineer Farrell,, Wesley Julian; Lic. No.: C42085 9304 VISTA SERENA      CYPRESS, CA 90630

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/8/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 7/14/2022 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Partial Approval RYAN SALAZAR
Wood Frame 10/6/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/2/2022 Corrections Issued ENRIQUE MIRELES
Green Building Rough 11/2/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/17/2022 Partial Approval ENRIQUE MIRELES
Drywall Nailing 12/2/2022 Approved MICHAEL LEWIS
Insulation 12/2/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 12/2/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 12/12/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/11/2023 Approved ENRIQUE MIRELES
Final 5/11/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 5/11/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/11/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 5/11/2023 Approved ENRIQUE MIRELES
Final 2/13/2024 Corrections Issued JOSE MACIAS
Special/Order Compliance 2/14/2024 Corrections Issued JOSE MACIAS
Final 2/27/2024 Partial Approval JOSE MACIAS
Final 3/8/2024 OK to Issue CofO DAVID FEILER
Service/Power Release 3/8/2024 Approved DAVID FEILER