10306 S GRAMERCY PL 90047
Certificate Information: 10306 S GRAMERCY PL 90047
- Application / Permit
- 22014-10000-01132
- Plan Check / Job No.
- B22LA04349
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DETACHED 2-CAR GARAGE TO ADU AND ADDITION OF (384 SF + 22 SF PORCH) PER LAMC 12.22A.33(c)-(d). ALL CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 6/7/2022
- Issuing Office
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2022 | VIVIAN LAO |
| Corrections Issued | 3/16/2022 | VIVIAN LAO |
| Plan Check Approved | 5/31/2022 | VIVIAN LAO |
| Issued | 6/7/2022 | APPLICANT |
| CofO in Progress | 1/23/2023 | ENRIQUE MIRELES |
| Permit Finaled | 2/7/2023 | DEROLD HAUFF |
| CofO Issued | 2/7/2023 | DEROLD HAUFF |
| Permit Finaled | 2/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/11/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 4/11/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2022 | CINDY QI |
| Sewer availability | Cleared | 4/28/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 7/8/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 7/8/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 7/8/2022 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 7/11/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/12/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/13/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 9/13/2022 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 9/13/2022 | Approved | MICHAEL LEWIS |
| Insulation | 9/14/2022 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 9/29/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 9/29/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 10/4/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/6/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/14/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 11/7/2022 | Approved | ENRIQUE MIRELES |
| Final | 11/23/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 11/23/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 11/23/2022 | Approved | ENRIQUE MIRELES |
| Final | 12/9/2022 | OK to Issue CofO | ENRIQUE MIRELES |