1920 W 82ND ST 90047

Certificate Information: 1920 W 82ND ST 90047

Application / Permit
22014-10000-01127
Plan Check / Job No.
B22LA04335
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETAHCED GARAGE TO ADU AND (20'-4" x 14'-9") 1-STORY ADDITION PER LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 11/4/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2022 APPLICANT
Assigned to Plan Check Engineer 4/15/2022 KHUONG TRUONG
Corrections Issued 4/16/2022 KHUONG TRUONG
Building Plans Picked Up 4/28/2022 APPLICANT
Plan Check Approved 10/18/2022 MINA HABILI
Issued 11/4/2022 APPLICANT
CofO in Progress 8/23/2023 ENRIQUE MIRELES
CofO in Progress 8/23/2023 ENRIQUE MIRELES
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/17/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/16/2022 JEANIE LAM
Sewer availability Cleared 6/16/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 7/21/2022 JEANIE LAM
Construction near power lines Cleared 10/1/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/3/2023 Approved ENRIQUE MIRELES
Sewer 4/17/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/1/2023 Approved STUART CHAPMAN
Underground Mechanical 5/30/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 6/2/2023 Approved ENRIQUE MIRELES
HVAC-Rough 6/2/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/2/2023 Approved ENRIQUE MIRELES
Green Building Rough 6/9/2023 Approved ENRIQUE MIRELES
Insulation 6/9/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/9/2023 Corrections Issued ENRIQUE MIRELES
Drywall Nailing 6/15/2023 Approved ENRIQUE MIRELES
Pre-Inspection 6/23/2023 Approved ENRIQUE MIRELES
Final 8/8/2023 Corrections Issued ENRIQUE MIRELES
HVAC-Final 8/8/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 8/8/2023 Approved ENRIQUE MIRELES
Service/Power Release 8/8/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/9/2023 Approved ENRIQUE MIRELES
Final 8/9/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 8/9/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/9/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 8/9/2023 Approved ENRIQUE MIRELES
Final 8/22/2023 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 8/22/2023 Approved ENRIQUE MIRELES