5143 N LOLETA AVE 90041
Certificate Information: 5143 N LOLETA AVE 90041
- Application / Permit
- 22014-10000-01118
- Plan Check / Job No.
- B22LA04320
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ALTERATION AND ADDITION TO THE REAR OF (E) ONE STORY SFD.
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/14/2022 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Applicant returned to address corrections | 12/9/2022 | LUKE GONZALES |
| Applicant returned to address corrections | 1/5/2023 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 1/13/2023 | DANIEL SMILEY |
| Plan Check Approved | 1/23/2023 | WEIJIAN HUANG |
| Issued | 1/23/2023 | APPLICANT |
| CofO in Progress | 6/17/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 6/21/2025 | DEROLD HAUFF |
| CofO Issued | 6/21/2025 | DEROLD HAUFF |
| Permit Finaled | 6/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/30/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2022 | TREVOR QUAN |
| Low Impact Development | Cleared | 11/29/2022 | AMMAR ELTAWIL |
| GPI Written Notices | Cleared | 1/5/2023 | FARSHAD ALIMOHAMADI |
| Grading Pre-Inspection | Cleared | 1/5/2023 | FARSHAD ALIMOHAMADI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
| Engineer | Tang,, Long Thanh; Lic. No.: C74481 | 5436 CADBURY RD WHITTIER, CA 90601 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/21/2023 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 9/25/2023 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 9/26/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/26/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/29/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/4/2023 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 10/4/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/4/2023 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/1/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/1/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 11/1/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/1/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 11/1/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 11/3/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/3/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 11/6/2023 | Approved | CRAIG VAUGHAN |
| Final | 12/21/2023 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Final | 12/21/2023 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 12/21/2023 | Not Ready for Inspection | ROY SPAULDING |
| Final | 6/13/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 6/13/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/17/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |